Wash. Admin. Code § 173-240-050

Current through Register Vol. 24-23, December 1, 2024
Section 173-240-050 - General sewer plan
(1) All general sewer plans required of any governmental agency before providing sewer service are "plans" within the requirements of RCW 90.48.110. Three copies of the proposed general sewer plan and each amendment to it must be submitted to and approved by the department before implementing the plan.
(2) The general sewer plan must be sufficiently complete so that engineering reports can be developed from it without substantial alterations of concept and basic considerations.
(3) The general sewer plan shall include the following information together with any other relevant data as requested by the department. To satisfy the requirements of the local government jurisdiction, additional information may be necessary.
(a) The purpose and need for the proposed plan.
(b) A discussion of who will own, operate, and maintain the systems.
(c) The existing and proposed service boundaries.
(d) Layout map including the following:
(i) Boundaries. The boundary lines of the municipality or special district to be sewered, including a vicinity map;
(ii) Existing sewers. The location, size, slope, capacity, direction of flow of all existing trunk sewers, and the boundaries of the areas served by each;
(iii) Proposed sewers. The location, size, slope, capacity, direction of flow of all proposed trunk sewers, and the boundaries of the areas to be served by each;
(iv) Existing and proposed pump stations and force mains. The location of all existing and proposed pumping stations and force mains, designated to distinguish between those existing and proposed;
(v) Topography and elevations. Topography showing pertinent ground elevations and surface drainage must be included, as well as proposed and existing streets;
(vi) Streams, lakes, and other bodies of water. The location and direction of flow of major streams, the high and low elevations of water surfaces at sewer outlets, and controlled overflows, if any. All existing and potential discharge locations should be noted; and
(vii) Water systems. The location of wells or other sources of water supply, water storage reservoirs and treatment plants, and water transmission facilities.
(e) The population trend as indicated by available records, and the estimated future population for the stated design period. Briefly describe the method used to determine future population trends and the concurrence of any applicable local or regional planning agencies.
(f) Any existing domestic or industrial wastewater facilities within twenty miles of the general plan area and within the same topographical drainage basin containing the general plan area.
(g) A discussion of any infiltration and inflow problems and a discussion of actions that will alleviate these problems in the future.
(h) A statement regarding provisions for treatment and discussion of the adequacy of the treatment.
(i) List of all establishments producing industrial wastewater, the quantity of wastewater and periods of production, and the character of the industrial wastewater insofar as it may affect the sewer system or treatment plant. Consideration must be given to future industrial expansion.
(j) Discussion of the location of all existing private and public wells, or other sources of water supply, and distribution structures as they are related to both existing and proposed domestic wastewater treatment facilities.
(k) Discussion of the various alternatives evaluated, and a determination of the alternative chosen, if applicable.
(l) A discussion, including a table, that shows the cost per service in terms of both debt service and operation and maintenance costs, of all facilities (existing and proposed) during the planning period.
(m) A statement regarding compliance with any adopted water quality management plan under the Federal Water Pollution Control Act as amended.
(n) A statement regarding compliance with the State Environmental Policy Act (SEPA) and the National Environmental Policy Act (NEPA), if applicable.

Wash. Admin. Code § 173-240-050

Statutory Authority: RCW 90.48.110. 00-15-021 (Order 00-09), § 173-240-050, filed 7/11/00, effective 8/11/00. Statutory Authority: Chapters 43.21A and 90.48 RCW. 83-23-063 (Order DE 83-30), § 173-240-050, filed 11/16/83. Statutory Authority: RCW 90.48.110. 79-02-033 (Order DE 78-10), § 173-240-050, filed 1/23/79. Formerly chapter 372-20 WAC.