Wash. Admin. Code § 173-240-180

Current through Register Vol. 24-20, October 15, 2024
Section 173-240-180 - Approval of construction changes

All wastewater facilities subject to the provisions of this rule must be constructed in accordance with the plans and specifications approved by the department. Any contemplated changes during construction, which are significant deviations from the approved plans, must first be submitted to the department for approval.

Wash. Admin. Code § 173-240-180

Statutory Authority: RCW 90.48.110. 00-15-021 (Order 00-09), § 173-240-180, filed 7/11/00, effective 8/11/00. Statutory Authority: Chapters 43.21A and 90.48 RCW. 83-23-063 (Order DE 83-30), § 173-240-180, filed 11/16/83. Statutory Authority: RCW 90.48.110. 79-02-033 (Order DE 78-10), § 173-240-180, filed 1/23/79. Formerly chapter 372-20 WAC.