Section 173-219-080 - Applying for a reclaimed water permit
(1) Reclaimed water permit application.
(a) Applications for reclaimed water permits shall be submitted to the lead agency no later than one hundred eighty calendar days before planned distribution of reclaimed water for use.
(b) Upon receipt of the application or renewal application for a permit, the lead agency must assess the application for completeness within ninety calendar days.
(c) Prior to submitting an application, the permit applicant must receive lead agency approval on a feasibility analysis under WAC 173-219-180.
(d) Prior to, or in conjunction with, submitting an application, the permit applicant must complete the required engineering report and submit it to lead agency for approval.
(2) Changes requiring new or supplemental reclaimed water permit application.
(a) Any person permitted for Class B reclaimed water generation proposing to generate Class A reclaimed water must file a new or supplemental application for any Class A use of reclaimed water not specifically authorized in the existing or active reclaimed water permit.
(b) Prior to, or in conjunction with, submitting the new or supplemental application, the permit applicant must:
(i) Submit new or revised planning and construction documents required in this chapter as necessary to describe any modifications of the existing reclaimed water facility.
(ii) Submit a copy of the new use agreements per WAC 173-219-290, unless the agreement for the new use is consistent with a standard use agreement that the lead agency has previously approved.
(3) Permit application and review fees.
(a) When health is the lead agency, health will charge a permit application fee in accordance with chapter 246-272 WAC. Health's permit fees may be based on or combined with the associated source water treatment permit.
(b) When ecology is the lead agency, ecology will charge a permit application fee in accordance with chapter 173-224 WAC.
(c) When health is nonlead agency and must review a portion of a permit application received by ecology, health will charge an hourly review fee under chapter 246-272 WAC.

Wash. Admin. Code § 173-219-080

Adopted by WSR 18-03-166, Filed 1/23/2018, effective 2/23/2018