For planning purposes, the total time to detect the release and shutdown the pipeline should be based on historic discharge data or, in the absence of such historic data, the operator's best estimate. At a minimum the total time to detect and shut down the pipeline must be equal to or greater than thirty minutes.
Each operator shall determine the worst case discharge and provide the methodology, including calculations, used to arrive at the volume in the contingency plan.
Wash. Admin. Code § 173-182-030
Statutory Authority: Chapters 88.46, 90.48, 90.56 RCW, and 2011 c 122 . 13-01-054 (Order 11-06), § 173-182-030, filed 12/14/12, effective 1/14/13. Statutory Authority: Chapters 90.56, 88.46, 90.48 RCW. 07-22-119 (Order 07-14), § 173-182-030, filed 11/7/07, effective 12/8/07; 06-20-035 (Order 00-03), § 173-182-030, filed 9/25/06, effective 10/26/06.