Current through Register Vol. 24-23, December 1, 2024
Section 16-131-040 - Initial application requirements(1) Persons seeking to produce CIEs must apply to the department of revenue as required under RCW 69.07.200. The initial endorsement is not valid until the department approves the applicant's submittals required under this section, inspects the CIE processing facility, and determines that the applicant and facility substantially complies with applicable laws and regulations.(2) Once the department receives the endorsement application from department of revenue's business licensing service, the department will contact the applicant and provide electronic copies of required forms for the applicant to complete.(3) Before the department will begin evaluation of an initial application, the applicant must submit the following: (a) Full facility plans as required under WAC 16-131-090;(b) A detailed floor plan or diagram of the CIE processing facility as required under WAC 16-131-090;(c) All documents required under WAC 16-131-050 for each initially proposed CIE;(d) Documentation verifying that the water supply meets standards in WAC 16-165-130.(4) Once the department determines that an initial applicant's submittal is complete and satisfactory, the department will contact the applicant to schedule an inspection. The CIE processing facility must be production ready at the time of inspection; perishable ingredients are not required to be in stock.(5) Following the inspection, the department will notify the applicant of its decision to approve or deny the endorsement. If approving the endorsement, the department will identify the CIE products approved for processing.Wash. Admin. Code § 16-131-040
Adopted by WSR 18-05-010, Filed 2/8/2018, effective 4/1/2018Amended by WSR 24-01-035, Filed 12/11/2023, effective 1/11/2024