Wash. Admin. Code § 136-18-030

Current through Register Vol. 24-23, December 1, 2024
Section 136-18-030 - Authorization of construction by county forces projects

Every proposed construction by county forces road project shall be a part of the county's annual construction program as defined in RCW 36.81.130 and WAC 136-16-020. Additions to the program, and/or substitutions in the program, may be made by unanimous action of the county legislative authority at any time as provided in RCW 36.81.130. No construction work shall be done on any project until it has been authorized by resolution of said authority. The resolution shall include:

(1) A brief description of the project;
(2) A vicinity map showing the location of the project and its limits, provided that in lieu of individual vicinity maps, a single vicinity map showing the location of all projects may be included with the resolution adopting the annual program;
(3) Identification of the project in terms of the officially adopted annual program;
(4) The county engineer's estimate of construction costs prepared pursuant to the completion of such preliminary engineering; and
(5) Construction plans as shall be necessary and sufficient.

Wash. Admin. Code § 136-18-030

Statutory Authority: Chapter 36.78 RCW. 09-23-044, § 136-18-030, filed 11/9/09, effective 12/10/09. Statutory Authority: Chapter 36.79 RCW. 99-01-021, § 136-18-030, filed 12/7/98, effective 1/7/99. Statutory Authority: RCW 36.78.070 and 36.79.060. 96-17-013, § 136-18-030, filed 8/12/96, effective 9/12/96. Statutory Authority: Chapter 36.78 RCW. 80-16-019 (Order 39), § 136-18-030, filed 10/29/80; 79-01-098 (Order 35), § 136-18-030, filed 1/3/79; Order 27, § 136-18-030, filed 1/27/76.