If interim lump sum reimbursement has been legislatively approved, when construction of the project is 50% complete and payment in two lump sums has been authorized, the following shall be submitted:
1. Schedule of values and calculations confirming 50% completion.2. Copies of bills and verification of payment (canceled checks or other means of verification as accepted by the reviewing authority) along with copies of original estimated costs to verify payment of 50% of those items for which reimbursement is being requested at that time.3. Interim affidavit of payment of claims.4. Further information as deemed necessary by the reviewing authority.6 Va. Admin. Code § 15-81-470
Derived From Virginia Register Volume 34, Issue 12, eff. 3/8/2018.Statutory Authority: 53.1-5, 53.1-80, and 53.1-82 of the Code of Virginia.