Section 4VAC25-130-819.15 - Auger mining; hydrologic balance(a) Auger mining shall be planned and conducted to minimize disturbances of the prevailing hydrologic balance in accordance with the requirements of 4VAC25-130-816.41 and 4VAC25-130-816.42.(b) All auger holes, except as provided in Paragraph (c) of this section, shall be-- (1) Sealed within 72 hours after completion with an impervious and noncombustible material, if the holes are discharging water containing acid-or toxic-forming material. If sealing is not possible within 72 hours, the discharge shall be treated commencing within 72 hours after completion to meet applicable effluent limitations and water-quality standards until the holes are sealed; and(2) Sealed with an impervious noncombustible material, as contemporaneously as practicable with the augering operation, as approved by the division, if the holes are not discharging water containing acid- or toxic-forming material.(c) Auger holes need not be sealed with an impervious material so as to prevent drainage if the division determines that-- (1) The resulting impoundment of water may create a hazard to the environment or public health or safety, and(2) The drainage from the auger holes will-- (i) Not pose a threat of pollution to surface water; and(ii) Comply with the requirements of 4VAC25-130-816.41 and 4VAC25-130-816.42.4 Va. Admin. Code § 25-130-819.15
Derived from VR480-03-19 § 819.15, eff. December 15, 1981; amended, eff. June 28, 1982; October 28, 1982; December 14, 1982; October 11, 1983; December 27, 1983; May 8, 1984; June 22, 1984; August 2, 1984; October 16, 1985; January 7, 1987; July 22, 1987; November 25, 1987; October 12, 1988; December 26, 1990; July 1, 1991; July 17, 1991; November 20, 1991; July 7, 1992; May 5, 1993; October 19, 1994.Statutory Authority
§§ 45.1-161.3 and 45.1-230 of the Code of Virginia.