Current through Register Vol. 41, No. 8, December 2, 2024
Section 4VAC25-130-778.17 - Permit term(a) Each application shall state the anticipated or actual starting and termination date of each phase of the surface coal mining and reclamation operation and the anticipated number of acres of land to be affected during each phase of mining over the life of the mine.(b) If the applicant requires an initial permit term in excess of 5 years in order to obtain necessary financing for equipment and the opening of the operation, the application shall--(1) Be complete and accurate covering the specified longer term; and(2) Show that the proposed longer term is reasonably needed to allow the applicant to obtain financing for equipment and for the opening of the operation with the need confirmed, in writing, by the applicant's proposed source of financing.4 Va. Admin. Code § 25-130-778.17
Derived from VR480-03-19 § 778.17, eff. December 15, 1981; amended, eff. June 28, 1982; October 28, 1982; December 14, 1982; October 11, 1983; December 27, 1983; May 8, 1984; June 22, 1984; August 2, 1984; October 16, 1985; January 7, 1987; July 22, 1987; November 25, 1987; October 12, 1988; December 26, 1990; July 1, 1991; July 17, 1991; November 20, 1991; July 7, 1992; May 5, 1993; October 19, 1994.Statutory Authority
§§ 45.1-161.3 and 45.1-230 of the Code of Virginia.