-- except for on site sewage or non-sewage disposal systems with less than 6,500 gpd capacity that are covered by the Wastewater System and Potable Water Supply Rules, or
-- are exempt from those rules, or
-- are existing indirect discharges of non-sewage waste.
Applicants with proposed New Indirect Discharges of Sewage that will discharge to Class B Waters must also document compliance with the applicable criteria of these rules before a draft permit can be distributed for public comment.
The applicant shall submit final detailed engineering plans and specifications and all other required data and information to provide evidence that these criteria have been met in order to obtain an indirect discharge permit.
As part of an application for an indirect discharge permit, an applicant may be required to demonstrate that a guarantee of continued operation of the system has been adequately provided. This guarantee may include trust indentures, contracts with a municipality, or other evidence which the Secretary determines to be sufficient to guarantee continued operation and maintenance of the system.
A sewerage system which uses a treatment system other than septic tanks is required to have a sludge management plan approved by the Agency. A Certificate for a Solid Waste Management Facility may also be required.
Any lagoons or storage vessels that require approval in accordance with 10 V.S.A. Chapter 43 must obtain that approval before an indirect discharge permit may be issued.
If, during the review of a renewal application, the Secretary determines that in-stream Nitrate nitrogen or Total Dissolved Phosphorus confidence values exceed the aquatic permitting criteria, or if biomonitoring results indicate a Significant Alteration of the Aquatic Biota in the receiving waters and these chemical or biomonitoring results are linked to the permitted indirect discharge, a contingency plan will be required. The contingency plan shall encompass the entire approved design capacity of the indirect discharge in the event the indirect discharge causes a significant alteration of the aquatic biota. The contingency plan shall comply with the following:
Under some conditions a permittee may be required to conduct a pre-discharge assessment by sampling the aquatic biota at the proposed control and impact areas before initiation of any site development activities to determine the relative difference between the two areas before any discharge has occurred. This will provide assurance that the post-discharge data will be useful for determining if a significant alteration of the aquatic biota has occurred.
The Secretary recognizes that situations may arise in which the primary sampling strategy of paired station comparison cannot be directly applied. The most probable situation would be the lack of appropriate reference or control areas. Alternative procedures for determining compliance with the aquatic biota criteria will be determined on a site specific basis.
Aquatic biota compliance monitoring shall be conducted by a qualified aquatic biologist or by qualified personnel under the direct supervision of a qualified aquatic biologist. In determining whether an aquatic biologist is qualified, the Secretary will consider the following education and experience criteria:
The wastewater collection, treatment, storage, and disposal system shall be operated and maintained at all times in a manner satisfactory to the Secretary and shall not cause:
A New Indirect Discharge of Sewage shall not cause a significant alteration of the aquatic biota in the receiving waters.
TABLE #1: METHODS FOR DETERMINING COMPLIANCE WITH THE AQUATIC PERMITTING CRITERIA
Compliance Method | Applicability (Maximum Design Capacity) | Stream Sampling Required? | Renovated Effluent Sampling Required? | Section of Indirect Discharge Rules |
Dilution | 20,000 gpd | No | No | 14-902 |
Treatment Index | 20,000 gpd | No | No | 14-903 |
Modified Site Specific | 30,000 gpd | Yes | No | 14-908 |
Site Specific (1) | No Limit | Yes | Yes | 14-904 |
Alternative Demonstration | No Limit | Yes | Yes | 14-914 |
(1) Site Specific includes In-Situ In-Ground Testing, Soil Extraction and Laboratory Testing, and Alternative In-Situ Testing |
The dilution method can be used for subsurface systems preceded by septic tanks that have a design capacity of 20,000 gallons per day or less and that indirectly discharge to streams. It is a presumptive method of demonstration that a proposed subsurface disposal system can comply with the Aquatic Permitting Criteria and the Vermont Water Quality Standards based on the ratio of the proposed indirect discharge of sewage to the low median monthly flow of the receiving stream.
A subsurface disposal system shall be presumed to meet the Aquatic Permitting Criteria and the Vermont Water Quality Standards if the ratio of the low median monthly flow of the receiving stream to the design capacity is 120:1 or greater. For a 6,500 gpd discharge, the low median monthly stream flow must be at least 780,000 gpd. For a 20,000 gpd discharge, the low median monthly stream flow must be at least 2,400,000 gpd.
A subsurface disposal system which has a treatment index of at least 150 points shall be presumed to meet the Aquatic Permitting Criteria and the Vermont Water Quality Standards.
There are four individual components to the treatment index for subsurface disposal systems. The sum of these components yields the total treatment index for the system. The four components are: vertical treatment, loading rate, horizontal treatment and dilution.
The vertical treatment component is attributed to only the unsaturated soils that may occur below the infiltrative surface of the disposal system. It represents the extent to which the effluent is treated by passage through these soil layers. It is based on the expectation that the longer the effluent remains in contact with the soil, the greater the potential for biological and chemical changes that provide renovation. The vertical treatment component is the sum of incremental calculations for each foot of unsaturated soil below the system to the seasonal high water table as determined in § 14-1101. The vertical treatment component can be determined in two ways:
Leachfield designs that use loading rates less than those allowed in § 14-1302 and § 14-1303 receive additional points towards the Treatment Index. The rationale for the loading rate component is that the sewage effluent is distributed over a greater land area than that required by these rules therefore providing an increased time of contact between the sewage effluent and unsaturated soils. The loading rate component is equivalent to 10 percent of the vertical treatment component point total, determined in subsection(l) above, for each 0.1 gallon per day per square foot that the design loading rate is less than the allowable loading rate, to a maximum of 50 percent of the vertical treatment component point total.
The horizontal treatment component is based on the shortest horizontal distance from any portion of the disposal field to the nearest point of natural groundwater discharge, whether it is a seepage zone or stream. The rationale for the horizontal component is that the greater the distance the sewage effluent must travel to the receiving stream, the more renovation the sewage effluent will receive. The horizontal component is calculated as follows:
The dilution component is the ratio of low median monthly stream flow to design flow at the point of compliance for the system. The rationale is that the larger the ratio of stream flow to design flow, the less the potential for the indirect discharge to significantly affect the stream chemistry and ultimately the aquatic biota. The dilution component is calculated by dividing the low median monthly stream flow at the point of compliance by the maximum design flow.
Figure #1 VERTICAL FACTOR vs. PERCOLATION RATE
TABLE #2: VERTICAL TREATMENT COMPONENT MULTIPLIERS
DEPTH OF UNSATURATED SOIL BELOW GROUND SURFACE USED FOR EFFLUENT RENOVATION | VERTICAL COMPONENT MULTIPLIER TO BE USED WITH VERTICAL FACTOR FROM FIGURE #1 |
0-12 inches 1 | 2.0 x |
12-24 inches 1 | 1.3 x |
24-36 inches | 1.0x |
36 - 48 inches | 0.8 x |
48 - 60 inches | 0.7 x |
> 60 inches | 0.7 x |
1 Can only be used for mound systems. |
TABLE #3: VERTICAL FACTORS FOR CALCULATING THE VERTICAL TREATMENT COMPONENT BASED ON SOILS EVALUATION METHOD
SOIL CLASS | SOIL TEXTURE (CONSISTENCE) | APPLICABLE VERTICAL FACTOR |
1 | Coarse Sand | 5 |
2 | Medium or Loamy Sand | 6 |
3 a. | Fine Sand or Loamy Fine Sand | 9 |
3 b. | Sandy Loam (loose; very friable) | 9 |
4 | Sandy Loam, Fine Sandy Loam, Loam, or Silt Loam (friable) | 48 |
5 a. | Sandy Loam, Fine Sandy Loam, Loam, or Silt Loam (firm) | 52 |
5 b. | Silt | 52 |
6 | Sandy Clay Loam, Silty Clay Loam, Clay Loam | 52 (requires mound system) |
On-site testing with sewage can cause pollution or health hazards if not conducted properly. Therefore, before an applicant or consultant may conduct on site testing with sewage, a pre-application testing authorization must be obtained from the Secretary by submitting a proposal for on-site testing with sewage. The proposal shall be submitted at least one month prior to the proposed testing period and include, at a minimum, the following:
TABLE #4: EFFLUENT CONCENTRATIONS FOR IN-SITU TESTING BY TREATMENT LEVEL
Effluent Concentrations (in mg/L) by Treatment Level (1) | ||||
Parameter | Septic Tank | Secondary | Secondary + (2) | Tertiary |
Biochemical Oxygen Demand (5-Day) | 175 (3) | 30 (3) | 15 (3) | 10 (3) |
Total Suspended Solids | 60 (3) | 30 (3) | 15 (3) | 10 (3) |
Total Dissolved Phosphorus | 8 | 5 | 5 | 0.5 |
Total Kjeldahl Nitrogen | 50 | N/A | N/A | 5 |
Ammonia (as N) | N/A | N/A | N/A | 1 |
Nitrate nitrogen | N/A | N/A | N/A | 5 |
Total Nitrogen (as N) | N/A | 15/25 (4) | 15/25 (4) | N/A |
(1) For in-situ effluent renovation testing, these should be considered minimum concentrations. (2) Secondary "plus" treatment level expected from recirculating filters. (3) When used for in-situ renovation testing, this minimum concentration is a recommendation only. (4) 15 mg/L for small aerated lagoon systems; 25 mg/L for larger aerated lagoon systems and activated sludge systems. |
The Modified Site Specific Compliance Method may be used to demonstrate compliance with the Aquatic Permitting Criteria for septic tank/leachfield systems with capacities of 30,000 gpd or less that discharge to streams using default values for concentrations of in-ground effluent parameters.
TABLE #5: DEFAULT CONCENTRATIONS TO BE USED IN TH DETERMINATION OF COMPLIANCE WITH THE AQUATIC PERMITTING CRITERIA USING THE MODIFIED SITE SPECIFIC METHOD
Parameter | Default In-Ground Effluent Concentration (mg/L) |
Nitrate Nitrogen | 60 |
Total Dissolved Phosphorus (TDP) | 0.14 |
Note: Use these default in-ground concentrations in the mass balance equation ($S14-912) to determine if the Aquatic Permitting Criteria have been met. |
TABLE #6 PHOSPHORUS REDUCTION FACTORS
Residence Time (days) | Factor |
0 to 5 | 1.0 |
6 to 10 | 0.90 |
11 to 15 | 0.80 |
16 to 20 | 0.75 |
21 or greater | 0.70 |
The appropriate factor from Table #6, Phosphorus Reduction Factors, is selected based on the calculated residence time. The phosphorus 5% exceedence value is multiplied by this factor and used in the mass balance equation listed in §14-912.
TABLE #7: STUDENT'S t DISTRIBUTION
for n, the number of degrees of freedom, equal to 1, 2,..., 30, 40, 60, 120; and for F(t)=0.60, 0.75, 0.80, 0.90, and 0.95. The t-distribution is symmetrical, so that F(-t) = 1-F(t)
n F | .60 | .75 | .80 | .90 | .95 |
1 | .325 | 1.000 | 1.376 | 3.078 | 6.314 |
2 | .289 | .816 | 1.061 | 1.886 | 2.920 |
3 | .277 | .765 | 0.978 | 1.638 | 2.353 |
4 | .271 | .741 | 0.941 | 1.533 | 2.132 |
5 | .267 | .727 | 0.920 | 1.476 | 2.015 |
6 | .265 | .718 | 0.906 | 1.440 | 1.943 |
7 | .263 | .711 | 0.896 | 1.415 | 1.895 |
8 | .262 | .706 | 0.889 | 1.397 | 1.860 |
9 | .261 | .703 | 0.883 | 1.383 | 1.833 |
10 | .260 | .700 | 0.879 | 1.372 | 1.812 |
11 | .260 | .697 | 0.876 | 1.363 | 1.796 |
12 | .259 | .695 | 0.873 | 1.356 | 1.782 |
13 | .259 | .694 | 0.870 | 1.350 | 1.771 |
14 | .258 | .692 | 0.868 | 1.345 | 1.761 |
15 | .258 | .691 | 0.866 | 1.341 | 1.753 |
16 | .258 | .690 | 0.865 | 1.337 | 1.746 |
17 | .257 | .689 | 0.863 | 1.333 | 1.740 |
18 | .257 | .688 | 0.862 | 1.330 | 1.734 |
19 | .257 | .688 | 0.861 | 1.328 | 1.729 |
20 | .257 | .687 | 0.860 | 1.325 | 1.725 |
21 | .257 | .686 | 0.859 | 1.323 | 1.721 |
22 | .256 | .686 | 0.858 | 1.321 | 1.717 |
23 | .256 | .685 | 0.858 | 1.319 | 1.714 |
24 | .256 | .685 | 0.857 | 1.318 | 1.711 |
25 | .256 | .684 | 0.856. | 1.316 | 1.708 |
26 | .256 | .684 | 0.856 | 1.315 | 1.706 |
27 | .256 | .684 | 0.855 | 1.314 | 1.703 |
28 | .256 | .683 | 0.855 | 1.313 | 1.701 |
29 | .256 | .683 | 0.854 | 1.311 | 1.699 |
30 | .256 | .683 | 0.854 | 1.310 | 1.697 |
40 | .255 | .681 | 0.851 | 1.303 | 1.684 |
60 | .254 | .679 | 0.848 | 1.296 | 1.671 |
120 | .254 | .677 | 0.845 | 1.289 | 1.658 |
infinity | .253 | .674 | 0.8416 | 1.282 | 1.645 |
The in-stream receiving water quality shall be determined in accordance with a Quality Assurance/ Quality Control (QA/QC) Plan submitted to and approved by the Secretary before the start of sampling. This QA/QC plan shall include, but is not limited to, the exact locations where the sampling will occur, the number and frequency of samples, the method of stream gaging, and the methods used for sample analysis.
There are two types of release systems for indirect discharging systems recognized in these rules. In an annual release system, the amount of effluent discharged per day is not regulated by the permittee based on the time of year. In a seasonal release system, the amount of effluent discharged is regulated by the permittee based on the season (winter or summer). Such systems necessitate the ability to store effluent. For the purposes of these rules, almost all systems are considered annual release systems.
An applicant for an indirect discharge permit using the annual release system shall collect and analyze a minimum of ten (10) in-stream receiving water samples at each point of compliance for a proposed indirect discharge in accordance with one of the two following procedures:
In addition to the 10 samples collected for the annual release system, an applicant for an indirect discharge permit using the seasonal release system must collect and analyze an additional eight (8) in-stream receiving water samples at each point of compliance during the months of January and February and at stream flows that are less than twice the median monthly flow, with at least two (2) additional samples collected in any of the other three Winter months of November, December and March.
Unless a shorter interval between consecutive samples at a particular compliance point is approved by the Secretary, there shall be a minimum of 4 days between samples. All stream samples shall be analyzed for all parameters listed under § 14-701 Aquatic Permitting Criteria.
For indirect discharges that overlap the point of compliance of another permitted discharge that is not operating at full permitted design capacity, the applicant may be required to evaluate the impact on water quality from the their proposed indirect discharge assuming the permitted discharge was operating at full design capacity.
For indirect discharges greater than 20,000 gpd of design capacity, the Secretary may request the applicant to evaluate the impact of the proposed development served by the proposed indirect discharge on the in-stream receiving water quality. This evaluation may be required when the in-stream receiving water quality will be affected by both the development and the indirect discharge or when construction of the development will affect the ability to conduct biological sampling to demonstrate compliance with § 14-2201.
When the proposed location for an indirect discharge is in a reach of stream that is also affected by other direct discharges, indirect discharges, and non-point discharges, the Secretary may withhold a determination on compliance with the Aquatic Permitting Criteria permitting limits for the indirect discharge application until a nutrient impact study is conducted. When this concern is evident from the location and data, the Secretary may require the applicant to conduct a nutrient impact study and evaluate the cumulative impact of all discharges on the in-stream receiving water quality.
All parameters shall be evaluated with the same number of samples, as practically possible. If additional sampling is conducted in-stream after the ten (10) initial samples, the data set for all parameters must be re-evaluated using the additional sampling data along with the initial sampling data. Any additional in-stream water quality samples must be analyzed for all required in-stream parameters listed under § 14-701 Aquatic Permitting Criteria.
and:
There are three components of the application for an Alternative Demonstration:
Following submittal of the complete application, and the public information meeting, the Secretary either approves, modifies, or denies the proposed Alternative Demonstration. The Alternative Demonstration shall be approved unless, in the opinion of the Secretary, it will cause an undue adverse effect on any beneficial value or use of the receiving stream, as defined by Water Quality Standards, or cause irreversible damage to the receiving stream. If the Secretary determines that the proposed mass nutrient loading may cause irreversible damage to the receiving stream, the Secretary may authorize the Alternative Demonstration at a lower loading rate than that requested by the applicant.
Authorization for the Alternative Demonstration shall be in the form of a written authorization from the Secretary that outlines the terms and conditions of the Alternative Demonstration. A copy of the written authorization shall be posted in the office of the town clerk in the town where the Alternative Demonstration is to take place.
Upon the Secretary's determination that the paired station analysis is not applicable to a particular stream location, the applicant may request that he/she be allowed to conduct an Alternative Demonstration utilizing a temporal analytical process, i.e. looking at one location over time. While the outline of study would be similar to that proposed for the paired station approach, four (4) years of background chemical and biological monitoring would be required, at a minimum, for an estimation of temporal variation at a specific stream location. Biological data collected during the course of the 18 month Alternative Demonstration would be judged against the background data for determination of Significant Alteration of Aquatic Biota. All such proposed Alternative Demonstrations must be developed by the applicant in conjunction with the Secretary.
The Secretary will not approve Alternative Demonstrations conducted on lakes, ponds or wetlands or to tributaries of lakes, ponds or wetlands within one mile of these water bodies unless the applicant can produce clear and convincing evidence during pre-Alternative Demonstration survey work that the nutrients discharged will exert their impact on the tributary in question and not the lentic environment.
The building sewer is that part of the drainage system extending from a building drain to a public sewer, private sewer, septic tank system, or other treatment system. A sewer serving one building will be considered a building sewer. All other sewers will be considered sewer collection systems.
The building sewer shall be constructed in a manner that will prevent leaking, breaking or clogging. Acceptable materials for the sewer are rubber-ring-jointed polyvinyl chloride (PVC) gravity sewer pipe, solvent-weld-jointed acrylonitrile-butadiene-styrene (ABS) solid wall sewer service pipe, or cast iron (CI) sewer service pipe. Other materials may be proposed to the Secretary for approval.
Building sewers shall be sized based on procedures outlined under §14-1003. Minimum building sewer size is 4 inches and minimum slope is 1/4 inch per foot.
Building sewers discharging to a collection sewer shall be connected through a manhole constructed in accordance with §14-1003 or with a wye fitting to direct flow and minimize in-line turbulence. The junction of more than two individual building sewers shall be made with a manhole.
Cleanouts shall be provided at each horizontal change in direction of the building sewer greater than 45 degrees and at intervals of not more than 100 feet. Building sewer changes in direction that exceed 45 degrees should be made with two 45 degree ells or long sweep fittings. Manholes are acceptable in lieu of cleanouts. Where building sewers to be installed at a depth of less than 3 feet under driveways are anticipated, extra heavy cast iron or other high strength pipe acceptable to the Secretary shall be required.
Building sewers shall meet the leakage standards prescribed in §14-1003.
Sewage pumps shall not be located inside buildings other than wastewater treatment facilities or buildings constructed as pump stations.
A sewer collection system is that system of sewers that transport wastewater from building sewers to the wastewater treatment/disposal system.
No connections of roof drains, area drains, foundation drains, cellar drains or other clean water sources or any storm drains will be allowed to building or collection sewers.
Building and collection sewers carrying raw sewage shall be sized as follows:
TABLE #8 PEAKING FACTORS
Design Flow (gpd) | Peaking Factor |
10,000 | 4.2 |
100,000 | 3.8 |
500,000 | 3.2 |
1,000,000 | 3.0 |
Kutter's Formula
In general, sewers should be sufficiently deep to receive sewage from basements and to prevent freezing. A bury depth of at least four feet should be maintained. This depth should be increased to at least five feet in areas to be plowed during Winter months. Where the designer cannot maintain these burial depths without significant expense, the engineer may propose a lesser depth of cover to the Secretary for approval with mitigating measures to protect the sewer.
All sewers shall be designed and constructed to provide a minimum velocity, when flowing full, of not less than 2.0 feet per second. Regardless of the formula used or friction factors used in the design of the sewers, all sewers shall be installed with not less than the slopes shown in Table #9, Minimum Slopes for Sewers. The following criteria shall also apply:
TABLE #9 MINIMUM SLOPES FOR SEWERS
Pipe Size (inches) | Slope Required (feet/100 feet) |
6 | 0.60 |
8 | 0.40 |
10 | 0.28 |
12 | 0.22 |
15 | 0.15 |
When a smaller sewer joins a larger one, the invert of the larger sewer should be lowered sufficiently to maintain the same energy gradient. An approximate method for securing these results is to place the 0.8 depth point of both sewers at the same elevation. Extensions of the sewer collection system should be designed for projected flows even when the diameter of the receipt sewer is less than the diameter of the proposed extension. The Secretary may require a schedule for future downstream sewer relief.
Generally, rubber-ring-jointed PVC, or ductile iron (DI) gravity sewer pipe of the proper class is acceptable. Other materials may be approved by the Secretary. The following criteria also apply:
Ledge, rock, boulders, and large stones shall be removed to provide a minimum clearance of four inches below and on each side of all pipe(s).
When tested, the leakage inward and outward of a gravity sewer including manholes shall not exceed 200 gallons per inch of pipe diameter per mile per day. Upon completion of construction, a sewer line shall be tested in accordance with one of the following procedures:
TABLE #10 MINIMUM TEST TIMES FOR VARIOUS PIPE SIZES
Nominal Pipe Size (inches) | Time (minutes/ 100 feet) | Nominal Pipe Size (inches) | Time (minutes/100 feet) |
3 | 0.2 | 21 | 3.0 |
4 | 0.3 | 24 | 3.6 |
6 | 0.7 | 27 | 4.2 |
8 | 1.2 | 30 | 4.8 |
10 | 1.5 | 33 | 5.4 |
12 | 1.8 | 36 | 6.0 |
15 | 2.1 | 39 | 6.6 |
18 | 2.4 | 42 | 7.3 |
FORMULAS AND ALLOW ABLE AIR LOSS STANDARDS
Calculate the required test time at a given allowable air loss as follows:
D2L | |
T = K x | Q |
Calculate air loss with a timed pressure drop as follows:
D2L | |
Q = K x | T |
Symbols: D = nominal size, inches
K = 0.371 W 10 [3] for inch-pound units
K = 0.534 W 10 [6] for S.I. units
L = Length of line of one pipe size, feet
Q = air loss, ft [3]/minute
T = time (in minutes) for pressure to drop 1.0 psi
An appropriate allowable air loss, Q, in cubic feet per minute, has been established for each nominal pipe size. Based on field experience, the Qs that have been selected will enable detection of any significant leak. Table #11 lists the Allowable Air Loss (Q) established for each pipe size.
TABLE #11 ALLOW ABLE AIR LOSS (Q) FOR VARIOUS PIPE SIZES
Nominal Pipe Size (inches) | Q (cubic feet/min) | Nominal Pipe Size (inches). | Q (cubic feet/min) |
3 | 2 | 21 | 5.5 |
4 | 2 | 24 | 6 |
6 | 2 | 27 | 6.5 |
8 | 2 | 30 | 7 |
10 | 2.5 | 33 | 7.5 |
12 | 3 | 36 | 8 |
15 | 4 | 39 | 8.5 |
18 | 5 | 42 | 9 |
For further information regarding the Air Testing procedures, refer to ASTM Standard C828-01. |
Manholes shall be installed at the end of each line, at all changes in grade, size or alignment, at all intersections, and at distances not greater than 3 00 feet.
The minimum diameter of manholes shall be 48 inches; large diameters are preferred for connection to large diameter sewers. A minimum access diameter of 30 inches shall be provided to allow for the equipment required for confined space access.
Flow channels shall be provided in the base of all manholes and the flow channel through manholes should be made to conform in shape and slope to that of the sewers.
Manholes shall be of the pre-cast concrete or poured-in-place concrete type. Manholes shall be waterproofed on the exterior. Rungs or steps shall be provided on the interior of each manhole to enable the structure to be easily and safely accessed.
Inlet and outlet pipes shall be joined to the manhole with a rubber-gasketed flexible watertight connection that allows differential settlement of the pipe and manhole wall to take place. Grouting is not an acceptable connection. All manhole connections, including building sewers, shall be constructed to this standard.
Watertight manhole covers are to be used wherever the manhole tops may be flooded by street runoff or high water. Locked manhole covers may be desirable in isolated locations where vandalism may be a problem.
All manholes shall be tested for leakage. Leakage testing of gravity sewers utilizing the water testing procedure takes into account the leakage from one manhole in the section. Otherwise, manholes shall be tested for leakage in accordance with one of the following procedures:
This method of testing manholes for leakage involves the use of a device for sealing the top of the manhole cone section and pumping the air out of the manhole, creating a vacuum and holding this vacuum for a prescribed period of time. The procedure for this test is as follows:
Sewers shall be laid at least ten feet horizontally from any existing or proposed water main. The distance shall be measured edge to edge. Where impossible or impractical, due to ledge, boulders or other unusual conditions, to maintain the ten foot sewer - water pipe horizontal separation between sewer and water lines, the water line may be in a separate trench or on an undisturbed earth shelf in the sewer trench provided that the bottom of the water line is at least 18 inches above the top of the sewer. Wherever impossible or impractical to maintain the 18 inch vertical separation, the sewer line shall be constructed to normal water line standards and pressure tested to 50 psi for 15 minutes prior to backfilling. No leakage shall be allowed for this test.
Sewers crossing water mains shall be laid beneath the water main with at least 18 inches vertical clearance between the outside of the sewer and the outside of the water main. When it is impossible or impractical to maintain the 18" vertical separation or where the sewer must be laid above the water main, the following criteria apply:
All sewage lift stations shall be located outside of buildings, except at wastewater treatment facilities and buildings constructed as pump stations.
Sewage pumping station structures and electrical and mechanical equipment shall be protected from physical damage from the one hundred (100) year flood. Sewage pumping stations should remain fully operational and accessible during the twenty-five (25) year flood.
Provision shall be made to facilitate removal of pumps, motors, and other mechanical and electrical equipment.
Submersible pumps shall be readily removable and replacement easily possible without dewatering the wet well or disconnecting any piping in the wet well.
Submersible pumps shall be designed specifically for raw sewage use, including totally submerged operation during a portion of each pumping cycle.
Lift stations receiving an average daily flow of less than 2,000 gal/day may be equipped with a single pumping unit, provided that replacement pumps are readily available, and one day's emergency storage is provided above the alarm level in the wet well. All other lift stations shall contain alternating duplex pumping units with each unit capable of pumping the maximum flow the station is expected to receive or shall contain other pumping arrangements considered sufficient by the Secretary to provide reliability.
For pumps handling raw sewage, except where grinder pumps are used, pumps shall be capable of passing spheres of at least three inches in diameter, and pump suction and discharge piping should normally be at least four inches in diameter. Pumps handling only settled wastewater shall be satisfactory to handle the particular wastewater to be pumped. Potable water pumps are generally not acceptable for pumping wastewater, except for highly treated effluent.
Generally, the pump shall be so placed that under normal operating conditions, it will operate under a positive suction head.
Electrical systems and components (e.g., motors, lights, cables, conduits, switch boxes, control circuits, etc.) in raw sewage wet wells, or in enclosed or partially enclosed spaces where hazardous concentrations of flammable gases or vapors may be present shall comply with the National Electrical Code [R ] requirements for Class I, Group D, Division 1 locations. In addition, equipment located in the wet well shall be suitable for use under corrosive conditions. Each flexible cable shall be provided with a watertight seal and separate strain relief. A fused disconnect switch located above ground shall be provided for all pumping stations. When such equipment is exposed to weather, it shall meet or exceed the requirements of weatherproof equipment as specified by the National Electrical Manufacturer's Association (NEMA). Standard 3R shall be used as a minimum and is specified in Publication #250-1997, "Enclosures for Electrical Equipment - 1,000 Volt Maximum." The address for NEMA is listed in § 14-2301 at the end of these rules.
The pumps selected shall be capable of providing the following pumping rates:
The pump control system shall be located away from the turbulence of incoming flow and pump suction.
The '2nd pump-on' level and 'alarm-on' level shall be at the same elevation.
Suitable shutoff valves shall be placed on the suction line of each pump except on submersible pumps.
Suitable shutoff and check valves shall be placed on the discharge line of each pump. The check valves shall be located between the shutoff valve and the pump. Check valves shall be suitable for the material being handled. Valves shall be capable of withstanding normal pressure and water hammer.
Valves may be located in wet wells only where single pump units are allowed. On all duplex unit pumping stations, the valves shall be in a separate valve pit adjacent to the wet well. This valve pit shall also contain a valved connection to allow the use of a portable pump for lift station bypassing during emergency conditions. The valve pit shall be provided with a drain to the soil or the wet well. If the pit is drained to the wet well, an effective method of preventing sewage from entering the pit during surcharged wet well conditions shall be provided. If the pit is drained to the soil, three feet of vertical separation shall be provided between the bottom elevation of the receiving device and the seasonal high groundwater level.
For lift stations handling raw sewage and receiving more than 20,000 gallons per day average design flow, the size of the wet well shall be such that with any combination of inflow and pumping, the cycle of operation of each pump will not be less than 5 minutes and the retention time in the wet well should not be more than 30 minutes at design flow. For raw sewage lift stations receiving less than 20,000 gallons per day, the retention time in the wet well should not be more than 30 minutes at average design flow. These requirements do not apply for lift stations handling only settled wastewater.
For all raw wastewater pump stations except submersible pump types, the wet well floor shall have a minimum slope of one to one to the hopper bottom. The horizontal area of the hopper bottom shall be not greater than necessary for proper installation and function of the inlet.
Ventilation may be either continuous or intermittent. Ventilation, if continuous, shall provide at least six complete air changes per hour, if intermittent, at least 30 complete air changes per hour.
For lift stations receiving less than 20,000 gallons per day design flow gravity ventilation is acceptable. For flows greater than 20,000 gallons per day design flow, forced ventilation shall be used. Forced ventilation may be either intermittent or continuous. Ventilation, if continuous, shall be capable of providing at least 12 complete air changes per hour, if intermittent, at least 30 complete air changes per hour. Air changes shall be forced into the wet well rather than exhausted from the wet well.
Upon completion of installation all tankage, including wet wells and storage tanks, shall be tested with clean water to demonstrate that the structures are watertight. The testing shall be conducted before the tankage and structures are backfilled. The test shall be conducted by completely filling the tankage to the top of the structures and providing a hydrostatic head of at least two feet above the surrounding groundwater level at the time of testing. The test shall be at least 24 hours, with no leakage resulting. If any leakage occurs during the test period the tanks shall be repaired and retested. At the Secretary's discretion, leakage testing may be required for a period longer than 24 hours.
Alarm systems shall be provided for pumping stations. The alarm shall be activated in cases of pump failure, use of the lag pump, high water in wet well, or other evidence of pump station malfunction. Audio and visual alarms shall be provided. Alarms shall be located in a normally frequented area.
The force main shall be sized to maintain a minimum hydraulic velocity of 2 feet per second under normal operating conditions. The minimum force main size shall be 1 1/2 inch diameter.
An automatic air relief valve shall be placed at high points in the force main to prevent air locking. In situations where the force main terminates at an elevation lower than the pumping station, a combination air release/vacuum release valve shall be installed at high points to protect the pumps and to prevent the remaining contents in the wet well from being siphoned out at the end of the pump cycle.
Force mains should enter the gravity sewer system at a point not more than 2 feet above the flow line of the receiving manhole.
Force mains and fittings, including reaction blocking, shall be designed to withstand normal pressure and pressure surges (water hammer).
Friction losses in force mains shall be based on the Hazen-Williams formula (below) or other acceptable method. Selected friction factors shall be representative of pipe materials selected, considering surface deterioration over the expected useful life of the pipe.
Hazen-Williams Formula:
v = 1.32 x C x R [063] x S [0.54]
where: R is the hydraulic radius
S is the slope of the energy grade line
C is the coefficient of roughness
There shall be a minimum 10 foot horizontal separation between water mains and force mains. A minimum 18 inch vertical separation between the outside pipe surfaces shall be maintained where force mains cross water mains. Force mains shall cross water mains at or near right angles with one full length of water pipe centered on the force main so both end joints are at maximum separation from the force main. Special structural support for the water main and the force main may be required.
Upon completion of construction of a force main, the line shall be pressure and leakage tested in accordance with the following procedure:
After the pipe has been laid, all newly laid pipe or any valved section thereof shall be subjected to a hydrostatic pressure of at least 1.5 x the highest working pressure in the section.
A leakage test shall be conducted concurrently with the pressure test as follows:
where: L is the allowable leakage, in gallons per hour; N is the number of joints in the length of pipeline tested; D is the nominal diameter of the pipe, in inches; and P is the average test pressure during the leakage test, in pounds per square inch gage.
TABLE #12: MINIMUM SEWAGE TREATMENT REQUIREMENTS BASED ON DESIGN CAPACITY AND DISPOSAL METHOD
Design Capacity (gallons per day) | Disposal Method | Minimum Treatment Level Required |
6,500 - 30,000 | Leachfield | Primary (Septic tank) |
30,001 - 50,000 | Leachfield | Secondary + (1) |
50,001 and greater | Leachfield | Tertiary |
6,500 and greater | Sprayfield | Secondary |
(1) Secondary 'plus' treatment level from recirculating sand/ textile filters. See Table #13. |
TABLE #13: EFFLUENT LIMITATIONS FOR EACH TREATMENT LEVEL
Effluent Limitation (in mg/L) by Treatment Level | ||||
Parameter | Septic Tank | Secondary | Secondary + (1) | Tertiary |
Biochemical Oxygen Demand (5-Day) | N/A | 30 (2) | 15 (3) | 10 (4) |
Total Suspended Solids | N/A | 30 (2) | 15 (3) | 10 (4) |
Total Dissolved Phosphorus | N/A | N/A | N/A | 0.5 (5) |
Total Kjeldahl Nitrogen | N/A | N/A | N/A | 5 (6) |
Ammonia (as N) | N/A | N/A | N/A | 1 (7) |
Nitrate nitrogen | N/A | N/A | N/A | 5 (8) |
Total Nitrogen (as N) | N/A | N/A | N/A | N/A |
(1) Secondary 'plus' treatment level from recirculating sand/textile filters. (2) Daily maximum. (3) Monthly average. (4) Monthly average; daily maximum is 18 mg/L (5) Monthly average; daily maximum is 1.0 mg/L (6) Monthly average; daily maximum is 10 mg/L (7) Monthly average; daily maximum is 2.0 mg/L (8) Monthly average; daily maximum is 10 mg/L |
Septic tanks shall be watertight, structurally sound, and constructed of materials not subject to extensive corrosion or decay. Reinforced concrete and fiberglass are considered the normal construction materials. Precast concrete tanks shall have a minimum wall thickness of 3 inches and shall be adequately reinforced to facilitate handling. When precast slabs are used as covers, they shall be watertight, have a thickness of at least 3 inches, and be adequately reinforced. For fiberglass tanks, the manufacturer may be required to substantiate the structural soundness of the tank by submitting an approved laboratory report which relates to structural testing of the tank.
Septic tanks shall be sized based on Table #14.
TABLE #14: SEPTIC TANK SIZING BASED ON DESIGN FLOW
Design Flow (gallons per day) | Required Septic Tank Capacity (gallons) |
Less than 750 | 1000 |
750 - 6,500 | 1.5 times the design flow |
Greater than 6500 | 0.75 times the design flow + 1,125 |
Where garbage grinders or disposals are proposed, the septic tank capacity shall be increased by a factor of 25 percent to provide additional storage for the expected increase in solids. |
When more than one septic tank is used in series the first tank shall be a minimum of 66% of the required septic tank capacity. The installation of septic tanks in parallel on a single building sewer or as part of a community sewage treatment and disposal system is not acceptable. Properly sized septic tanks installed on parallel building sewers are acceptable.
Pumping of sewage to septic tanks without provisions for energy dissipation is not acceptable because this will reduce the size of the solids being received at the tanks and will cause surging through the tanks, both of which reduce the effectiveness of the tanks.
Septic tanks shall be located to meet the minimum isolation distances listed in Table #21, Isolation Distances. Septic tanks shall also be located to facilitate removal of sludge and scum by scavenger vehicles.
Adequate access must be provided to each compartment of the tank for inspection and cleaning. Both the inlet and outlet devices shall be accessible. Access shall be provided to each compartment by means of either a removable cover or a manhole of at least 16 inches in diameter. Each tank shall have one manhole of at least 16 inches in diameter. Each tank shall have one manhole access to grade. Covers should be tight fitting and exposed covers should be designed to prevent entry by children.
The inlet invert shall enter the tank at least 3 inches above the liquid level in the tank to allow for momentary rises in liquid level during discharges to the tank. A vented inlet tee, or baffle, shall be provided to direct the incoming wastewater downward. It shall penetrate at least 6 inches below the liquid level, but in no case shall the penetration be greater than that allowed for the outlet device.
It is important that the outlet device penetrate just far enough below the liquid level of the septic tank to provide a balance between sludge and scum storage volume. The outlet device should generally extend to a distance below the surface equal to 40 percent of the liquid depth. For horizontal, cylindrical tanks, this should be reduced to 35 percent.
The most downstream community septic tank in series shall be equipped with a properly sized septic tank effluent filter.
Upon completion of installation all tankage shall be tested with clean water to demonstrate that the structures are watertight. The testing shall be conducted, before the tankage and structures are backfilled, by completely filling the tankage to the top of the structures and providing a hydrostatic head of at least two feet above the level of the surrounding groundwater at the time of testing. The test shall be at least 24 hours, with no leakage resulting. If any leakage occurs during the test period the tanks shall be repaired and retested. At the Secretary's discretion, a leakage test may be required for a period longer than 24 hours.
An approved grease interceptor shall be installed in the waste line from sinks, drains, and other fixtures or equipment in restaurants, cafeterias, bars and clubs, hotel, factory or school kitchens, or other establishments where grease introduced into the drainage system would be of particular concern.
Each grease interceptor shall be located outside buildings and connected to the wastewater system at a location prior to the septic tank. Each grease interceptor shall be so installed and connected that it is, at all times, easily accessible for inspection, cleaning and removal of the intercepted grease.
For the purpose of the section, the term fixture shall include each plumbing fixture, appliance, apparatus or other equipment required to be connected to a grease interceptor.
TABLE #15: GREASE INTERCEPTOR CAPACITY BASED ON NUMBER OF CONNECTED FIXTURES AND REQUIRED FLOW RATES
Total Number of Fixtures Connected | Maximum Capacity of Fixtures Connected (gallons) | Required Flow Rate (gallons per minute) | Grease Retention Capacity (pounds) |
1 | 50 | 20 | 40 |
2 | 65 | 25 | 50 |
3 | 90 | 35 | 70 |
4 | 125 | 50 | 100 |
Each grease interceptor shall have a minimum capacity of 125 gallons plus 2.5 gallons of capacity for each seat in a restaurant, dining hall, or cafeteria or a minimum capacity as calculated by the above table, whichever is greater.
Each grease interceptor shall be constructed of durable materials and shall have a full size gas-tight cover which can be easily and readily removed. Each grease interceptor shall be vented and each fixture discharging into a grease interceptor shall be individually trapped and vented in an approved manner.
Sand filters are intended for use following septic tanks. For a reduction in the disposal area required, an intermittent sand filter effluent quality must meet secondary effluent standards, with no more than 30 mg/ L biochemical oxygen demand (BODS) and no more than 30 mg/L total suspended solids (TSS). For recirculating sand filters, the effluent standards are no more than 15 mg/L biochemical oxygen demand (BODS) and no more than 15 mg/L total suspended solids (TSS) for a reduction in the disposal area required.
Note: Filtrate disposal areas located more than twenty five (25) feet apart may be considered hydraulically isolated from each other for the purpose of this subsection.
In addition to the applicable requirements of (a) - (f) above, the following system specific criteria apply to design of intermittent sand filters:
TABLE #16: FILTER MEDIA SPECIFICATIONS FOR INTERMITTENT SAND FILTER
SIEVE NUMBER | OPENING (mm) | PERCENT PASSING (by weight) |
3/8 | 9.50 | 100 |
4 | 4.75 | 95-100 |
8 | 2.38 | 80-100 |
16 | 1.19 | 45-85 |
30 | 0.59 | 15-60 |
50 | 0.297 | 3-15 |
100 | 0.149 | 0-4 |
In addition to the applicable requirements of (a) - (f) above, the following system specific criteria apply to design of recirculating filters:
TABLE #17: FILTER MEDIA SPECIFICATIONS FOR RECIRCULATING SAND FILTER
SIEVE NUMBER | OPENING (mm) | PERCENT PASSING (by weight) |
3/8 | 9.50 | 100 |
4 | 4.75 | 60-100 |
8 | 2.38 | 7-75 |
16 | 1.19 | 0-5 |
30 | 0.59 | 0-3 |
50 | 0.297 | 0-2 |
The recirculation tank receives septic tank effluent and the discharge from the filter. The recirculation tank and dosing system shall comply with the following requirements:
Each system shall have a minimum of three (3) treatment cells contained in a minimum of two separate and independent treatment lagoons. A floating baffle or other separation device may be installed in the second treatment lagoon. Each lagoon shall be capable of being de-watered separately, while maintaining treatment in the other lagoon.
To prevent any accidental discharge of waste to waters of the State, all waste lagoons including treatment and effluent storage lagoons, shall have a minimum freeboard of three (3) feet at all times from the lowest portion of the top of embankment to the design water level. If the lagoon is also permitted under 10 V.S.A. Chapter 43 and a freeboard of more than three feet is necessary to provide for structural safety of impoundment then the greater freeboard shall limit the high water level. Tank storage structures are required to have a minimum of two (2) feet of freeboard.
All lagoons shall be designed with underdrains and gas relief vents beneath the required impermeable liner.
All waste treatment and storage lagoons shall be lined with a man-made impermeable material approved by the Secretary. The liner shall be adequately protected from chemical and physical damage and deterioration with a proper base and cover. The minimum thickness of the liner shall be 30 mil. Exposed liners may be permitted if the applicant makes adequate demonstration of the long-term protection of the liner from deterioration. Once the liner is installed, it shall be tested for leakage in accordance with the manufacturer's specifications. If the lagoon is also permitted under 10 V.S.A. Chapter 43 and a lesser leakage rate is necessary to provide for structural safety then the lesser leakage rate shall control the design.
Each system will have sufficient aeration tubing or diffusers on the site to replace the entire aeration system in the largest treatment cell.
Each system shall have the ability to expel water from the aeration lines without dewatering the lagoons or forcing the water to exit above the lagoon water surface. A separate drain is required for each header or header set in a multi-header system.
The system shall include a provision for gas cleaning of aeration lines, including subheaders.
Each system shall have equipment on site capable of flexing aeration tubing for cleaning.
All required effluent storage volume shall be separate and independent from any treatment lagoon.
Aerated lagoon systems shall be designed with a K e rate of not greater than 0.11, unless the Secretary approves the use of another value as proposed by a professional engineer. This K e rate reflects an appropriate decay rate and an allowance for short-circuiting across the system. (See also TR-16, Guides for the Design of Wastewater Treatment Works).
Overall lagoon size and volume is determined by adding 15% for ice and sludge whose accumulation would decrease the detention time in the lagoon.
If the liner sides are covered, then the entire treatment or storage lagoon side slopes shall be lined with riprap.
The aeration system should be designed with capacity to provide FOUR (4) pounds of oxygen per pound of BOD applied. The field oxygen transfer rate (FOTR) for mechanical systems and the field oxygen transfer efficiency for diffuser systems shall be calculated using an appropriate "aeration adjustment equation" and an alpha factor which is characteristic of the system being proposed. The standard oxygen transfer rate (SOTR) or standard oxygen transfer efficiency of the proposed system shall be based on the results of laboratory testing of the proposed equipment and the liquid depth of the proposed lagoons.
Liquid level indicators shall be installed in each storage and treatment lagoon.
All wastewater lagoon systems shall have the capability of measuring and recording the totalized influent wastewater flow and the totalized effluent flow discharged.
All mechanical treatment facilities, except those smaller units (< 50,000 gpd) preceded by septic tanks, will provide flow and organic load equalization tanks ahead of, or incorporated into, the first biological treatment unit, and shall also provide an aeration system sufficient to maintain complete mix with no settling and to prevent the wastewater from becoming septic. Air mixing equipment should provide 10-30 Standard Cubic Feet Per Minute (scfm) per 1000 cubic feet of storage volume. The sizing of the equalization tank(s) must be large enough to assure that flows reaching downstream treatment units do not exceed 200% of the design average flow rate. Equalization tanks shall have a minimum of two (2) feet of freeboard.
All mechanical treatment plants preceded by a lagoon shall be constructed with the capability to divert substandard effluent from the mechanical treatment processes back to the initial lagoon instead of the effluent storage pond.
All unit operation and processes shall have a minimum of two independent units, each with a minimum of 75% of design capacity and capable of independent operation. If the process is designed for normal operation utilizing more than two units, then a backup unit with a capacity equal to the capacity of the largest unit and capable of replacing any of the individual units shall be provided. All unit processes must be provided with a reliable means of properly proportioning the sewage flow to each unit.
Mechanical secondary and tertiary plants shall be provided with one of the following reliability features:
Each facility shall provide a minimum capability for 30 days of aerobic sludge digestion and additional capacity to store six (6) months volume of treated sludge. The requirement for six months storage capability shall be waived if the facility has a sludge disposal contract approved by the Secretary.
All sludge removed from the sewage treatment facility shall be disposed of at locations approved by the Residuals Management Section of the Department of Environmental Conservation. The permittee(s) shall comply with the reporting procedures specified in the Certification from the Residuals Management Section or approved Sludge Management Plan.
Upon completion of installation all tankage shall be tested with clean water to demonstrate that the structures are watertight. The testing shall be conducted before the tankage and structures are backfilled. The test shall be conducted by completely filling the tankage to the top of the structures and providing a hydrostatic head of at least two feet above the surrounding groundwater level at the time of testing. The test shall be at least 24 hours, with no leakage resulting. If any leakage occurs during the test period the tanks shall be repaired and retested. At the Secretary's discretion, a leakage test may be required for a period longer than 24 hours.
TABLE #18: TREATMENT REQUIREMENTS FOR RECLAIMED WATER USE
PARAMETER (units) | LIMITS |
E. Coli Bacteria (per 100ml) | 2.2 (a) 25 (b) |
Turbidity (NTU) I | 2.0 (c) 5.0 (d) |
Residual Chlorine (mg/L) | 1.0 (e) |
BOD5 (mg/L) | 10.0 (c) |
TSS (mg/L) | 5.0 (c) |
Footnotes: (a) Geometric mean of 5 samples at point of use (b) Single sample cannot exceed this level at point of use (c) Monthly average prior to disinfection (d) Single sample cannot exceed this level (e) Minimum concentration required |
A written guarantee from the manufacturer stating that the unit will meet the prescribed effluent limitations for Escherichia coli as stated in the Vermont Water Quality Standards (surface water standard) may be required.
The consultant may propose other disinfection systems for review and approval by the Secretary. These systems will be evaluated based on the information supplied by the consultant which should include complete documentation of system by the manufacturer, evidence of reliable performance in systems installed in similar working environments including monitoring data and evidence that regulatory effluent limitations can be met, and establishing that the proposed system is as reliable as other disinfection systems allowed under these rules.
A written guarantee from the manufacturer stating that the unit will meet the prescribed effluent limitations for Escherichia coli as stated in the Vermont Water Quality Standards (surface water standard) may be required.
Except for pump stations and sewerlines, all components of sewage treatment systems shall not be located closer than 300 feet to any property line, habitation, or area frequented by the public, unless a reduction in distance is approved in accordance with paragraph (b) below. The applicant must obtain legal easements restricting public access if any component is to be located within 300 feet of a property line, habitation, or area frequented by the public, unless a reduction in this distance is granted.
The minimum isolation distance may be reduced from 300 feet to 100 feet if the applicant demonstrates to the satisfaction of the Secretary that all components will be enclosed and have operating mechanical equipment as necessary to prevent odors and health hazards from aerosols escaping the facility. The applicant may be required to demonstrate successful performance of similar controls under severe climatic conditions.
Effluent storage lagoons or tanks may be located a minimum of 150 feet from a property line, habitation or area frequented by the public if designed and operated in accordance with the following conditions:
TABLE #19: LEACHFIELD LOADING RATES - PART I: BASIC SIZING CRITERIA
SOIL CLASS | TYPICAL DEPOSITIONAL ENVIRONMENT | SOIL TEXTURE a (CONSISTENCE) | TYPICAL RANGE OF PERCOLATION RATES (min./inch) | MAXIMUM WASTEWATER LOADING RATE (gpd/ft 2) |
1. | Glaciofluvial or Alluvial | Coarse Sand | 0-3 | 0.9 |
2. | Glaciofluvial or Alluvial; | Medium Sand or Loamy Sand | 1-10 | 0.9 |
3a. | Alluvial | Fine Sand or Loamy Fine Sand | 5-30 | 0.7 |
3b. | Glacial Till | Sandy Loam (Loose; Very Friable) | 5-30 | 0.7 |
4. | Glacial Till | Sandy Loam, Fine Sandy Loam, Loam, or Silt Loam (Friable) | 30-45 | 0.5 |
5a. | Glacial Till | Sandy Loam, Fine Sandy Loam, Loam, or Silt Loam (Firm) | 45-60 | 0.35 |
5b. | Lacustrine or Alluvial | Silt | 45-60 | 0.35 |
6. | Lacustrine or Marine | Sandy Clay Loam; Silty Clay Loam; or Clay Loam | 60-120 | 0.24 b |
7. | Lacustrine or Marine | Sandy Clay; Silty Clay; or Clay | 120 + | Not Suitable |
a Per USDA - Soil Conservation Service Soil Textural Classes (see Figure Consistence is based on moist, in-situ conditions. #2). | ||||
b Requires a mound disposal system. |
TABLE #19: LEACHFIELD LOADING RATES - PART II: SIZING ADJUSTMENT
If any of the soil layers within the zone of interest have any of the following characteristics, then the maximum loading rates for those layers must be adjusted as indicated below. It is possible that a soil layer different than that identified as limiting before the adjustment is made will control the maximum loading rate, or the suitability of the site for sewage disposal.
However, if all other criteria for a mound or soil replacement system are met, then either 3(a) or 3(b) may be used to provide up to two feet of the required three feet of suitable soil above seasonal high water table, with mound specified sand providing the remaining foot of soil.
FIGURE #2: SOILS TRIANGLE
The effluent distribution system for all subsurface leachfields and for mound systems must meet the following requirements:
TABLE #20: REQUIRED DISPOSAL AREA WITH INCREASED DEPTH OF STONE
Depth of Stone | Percentage of Standard Disposal Area Required |
18" | 75% |
24" | 66% |
TABLE #21: ISOLATION DISTANCES
The following isolation distances apply regardless of property line location and ownership. These distances may be reduced when it is evident that the distance is unnecessary to provide protection and may be increased if greater distance is necessary to provide adequate protection.
Minimum Horizontal Isolation Distance (feet) | ||||
ITEM | SEWER | SEPTIC TANK | DISPOSAL FIELD | SPRAY FIELD |
Drinking Water Supply Source | see (a) | see (a) | ||
Drilled Well | 50 | 200 $(see (b)$) | 200 $(see (b)$) | |
Gravel Pack Well, Shallow Well or Spring | 75 | 75 | 200 $(see (b)$) | 200 $(see (b)$) |
Standing Water (Lake or Pond) | 25 | 25 | 200 | 100 |
Streams and Rivers (includes groundwater seeps) | 10 | 25 | 150 | 100 |
Drainage Swales / Roadway Ditches | C | C | 25 | 100 |
Main or Municipal Water Lines | see (c) | 50 | 50 | 200 |
Service Water Lines | see (c) | 25 | 25 | 200 |
Roads, Driveways, Parking Lots | see (d) | 5 | 10 | 200 |
Top of Bank or to Slope Greater than 30% | C | 10 | 50 | see (e) |
Property Line | 10 | 10 | 25 $(see (f)$) | 200 |
Trees | 10 | 10 | 10 | --- |
Other Disposal Field | C | C | 10 | 200 |
Foundations, Footing Drains or Curtain Drains | C | 10 | 35 $(see (g)$) | 200 |
Public Community Water System | see (h) | see (h) | see (h) | see (h) |
Suction Water Line | 50 | 50 | 100 | 200 |
(a) Separation between drinking water sources and leachfields or sprayfields shall be determined by the methods in the Vermont Water Supply Rule and guidance from the Secretary. | ||||
(b) Presumes that geological conditions exist that would prevent the movement of contaminants from the indirect discharge to the water supply. If a hydrogeologic connection exists between the indirect discharge and a water supply, see $S 14-2102 of these rules for further requirements. | ||||
(c) Separation of pressure water lines (considered to be part of a public water system as defined by the Vermont Water Supply Rule) and sewer lines shall comply with the requirements of the Vermont Water Supply Rule. Separation of pressure water lines considered to be "service connections" and sewer lines shall comply with the Vermont Plumbing Code. | ||||
(d) Sewer lines under roads, driveways or parking lots may require protective conduits or sleeves. | ||||
(e) Thirty percent (30%) is the maximum slope for the wetted area of a spray field. | ||||
(f) For mound disposal systems, the limit of mound fill must be 50 feet from any downgradient property line and 10 feet from any property lines on the side or uphill. | ||||
(g) If the foundation or curtain drain is downgradient of the disposal field, there must be a minimum of 150 feet between the drain and the disposal field, assuming that the effluent discharged will not enter the drain. Up gradient of the disposal field the distance shall be a minimum of20 feet and preferably 35 feet if possible. These distance may be reduced if the applicant provides adequate data and analysis to show that the effluent from the disposal field will not enter the drain. The distances may be increased if there is potential for effluent to enter the drain. | ||||
(h) Contact the DEC Water Supply Division, 103 South Main Street, The Old Pantry Building, Waterbury, Vermont 05671-0403 Phone: (802) 241-3400 |
The fill material used shall meet one of the following three specifications listed in Tables #22(A), #22 (B) & #22(C). Interpolation of analyses is not permitted. Fill material Type B is ASTM Specification C-33.
TABLES #22(A) (B) & (C): SAND SPECIFICATIONS
TABLE #22(A): Type A Sand Specifications | ||
Sieve Number | Opening (mm) | Percent Passing (by Weight) |
10 | 2.000 | 85 - 100 |
40 | 0.420 | 25 - 75 |
60 | 0.240 | 0 - 30 |
100 | 0.149 | 0 - 10 |
200 | 0.074 | 0 -5 |
TABLE #22(B): Type B Sand Specifications | ||
Sieve Number | Opening (mm) | Percent Passing (by Weight) |
4 | 4.750 | 95 - 100 |
8 | 2.380 | 80 - 100 |
16 | 1.190 | 50 - 85 |
30 | 0.590 | 25 - 60 |
50 | 0.297 | 10 - 30 |
100 | 0.149 | 2 - 10 |
TABLE #22(C): Type C Sand Specifications | ||
Sieve Number | Opening (mm) | Percent Passing (by Weight) |
10 | 2.000 | 85 - 100 |
40 | 0.420 | 30 - 50 |
200 | 0.074 | 0 - 10 |
The investigation of soil conditions and surface features must include, at a minimum, the following components:
The hydrogeologic investigation must include, at a minimum, the following components:
TABLE #23: ALLOWABLE SPRAY APPLICATION RATES BASED ON EFFLUENT TREATMENT
Treatment Level: BODS I TSS | Application Rate (inches per week) | Equivalent gallons per day (per acre of wetted area) |
30 mg/L (1) 30 mg/L (1) | 2 | 7,758 |
15 mg/L (2) 15 mg/L (2) | 3 | 11,637 |
10 mg/L (3) 10 mg/L (3) | 4 | 15,516 |
(1) Daily Maximum. (2) Required treatment level from recirculating sand / textile filter - see Table # 13 (p.92) (3) Tertiary Treatment required see Table #13 (p. 92) |
Capacity = 30-day Peak Flow - [0.80 (TSV)]
Where: 30-day Peak Flow is the maximum metered influent flow, in gallons, for the system for any 30 consecutive days during the period April 1 [st] - May 15th.
TSV is the total storage volume (gallons)
There are two options for providing effluent disinfection for spray disposal systems:
When designing wastewater treatment and disposal systems for projects generating non-sewage wastewater the designer will establish hydraulic flows, solids loadings, and organic loadings. Flow and loading variations, both cyclical and chronological, will be considered in all specialized designs. Whenever applicable, normal domestic sewage strength will be the standard of comparison for all non-sewage wastewater. Normal domestic sewage strength after septic tank treatment is typically characterized by a biochemical oxygen demand (5-day) concentration of< 400mg/L and a total suspended solids concentration of< 150 mg/L.
When the non-sewage wastewater contains non-conventional pollutants (anything other that those found in domestic sewage) and/or conventional pollutants in concentrations substantially greater than in domestic sewage the designer will report each pollutant and its concentration and loading, in the permit application. The designer will also render his/her professional opinion as to the fate of these pollutants after passage through the proposed wastewater treatment system and their impact on the quality of ground and surface waters. If any of the pollutants are considered hazardous or toxic waste the application will be reviewed by hazardous and toxic waste experts in the Department. They may recommend that jurisdiction of the system remain under these rules or claim jurisdiction over the project based on Vermont hazardous and toxic waste laws.
The Secretary may consider non-sewage wastewater from food processing facilities discharged to agricultural lands as fertilizer amendments. The Secretary may issue permits for these non-sewage discharges with adequate conditions and monitoring considered necessary to prevent a violation of the Water Quality Standards. The Secretary may establish guidelines and procedures for the design and operation of different types of non-sewage waste treatment facilities.
In the design of all non-sewage wastewater treatment systems the Secretary will require a level of design, construction and operation reliability to ensure that the proposed system can function as intended without violation of permit conditions or Vermont Water Quality Standards.
Monitoring of the treatment systems for indirect discharges shall be conducted at the frequencies specified in the permit. Monitoring requirements shall be commensurate with the nature of the indirect discharge, the size of the system and the potential for alteration of the chemistry and aquatic biota of the receiving waters.
All operational testing, effluent monitoring and ground and surface water monitoring shall be conducted following procedures for sampling and analysis in accordance with a Quality Control/Quality Assurance Plan submitted to and approved by the Secretary.
Annually, during the month of April (unless otherwise specified by the Secretary), a professional engineer shall thoroughly inspect the complete sewage collection, treatment and disposal system for any evidence of failure and report all necessary repairs and maintenance required for the proper operation of the. system. The engineer's inspection report shall be submitted to the Secretary by June 1st for review and approval unless otherwise specified by the Secretary.
During the system's annual inspection the depth of sludge and scum shall be measured in all septic tanks. The septic tanks shall be pumped if:
If hydrogeologic connections are deemed to exist between a water supply and an indirect discharge as proposed, the Secretary shall apply the following criteria which, if met, will allow approval of the discharge:
The Public Water Source Protection Area (PWSPA) refers to the surface and subsurface area, designated by the Secretary, surrounding a water well or well field supplying a public water system through which contaminants are likely to move toward and reach such water well or well field.
All sewage collection facilities constructed within a PWSPA shall comply with the standards listed below. However, Professional Engineers are encouraged to use equally or more effective technologies or practices in the design of systems under these guidelines. When proposing an alternative design, the engineer shall state the basis of design and provide evidence to substantiate its reliability. The engineer may also propose materials other than those specified here for acceptance by the Secretary.
In order to demonstrate compliance with the criterion of no significant alteration of the aquatic biota, the assessment of periphytic chlorophyll accumulation must indicate no significant differences between or among stations at the 99.9% probability level (P [less than or equal] 0.001 two-tailed test).
The sampling and testing procedure for determining the periphytic chlorophyll accumulation is outlined in §14-2202. The Mann-Whitney U test, a non-parametric equivalent of the Student's T-test, shall be used to determine if there are significant differences between control and impact stations. Significant differences at P: 0.001 (two-tailed test) shall indicate a significant alteration of the aquatic biota (SAAB).
The following four metrics are used to assess the macroinvertebrate community relative to the criterion of no significant alteration of the aquatic biota:
The procedure for determining the Pinkham-Pearson Coefficient of Similarity (PPCS) metric is outlined in § l 4-2202(b).
The procedure for determining the Biotic Index (BI) metric is outlined in §14-2202.
The procedure for determining the Ephemeroptera - Plecoptera - Trichoptera Taxa Richness (EPT) metric is outlined in §14-2202.
The procedure for determining the Relative Abundance metric is outlined in §14-2202.
The Secretary will review all pertinent stream data and factors affecting the monitoring locations prior to making a finding that a significant alteration of aquatic biota has occurred due to the indirect discharge.
If the macro invertebrate assessment results in no significant determination due to excessive data variability the following process shall be followed:
Three testing periods shall be used in determining whether or not significant differences in chlorophyll accumulation between stations is in evidence: Spring (May 15 - June 30), Summer (July 15 - August 31) and Fall (September 15 - October 31). Testing is normally required only during the Summer period but the Secretary reserves the right to require testing during the Spring and Fall periods.
Three samplers shall be deployed at each station at locations approved by the Secretary. Each sampler shall include four rectangular granitic blocks (1/4" W 1" W 3") for a total of 12 station replicates (n = 12). Samplers shall be left in-stream for a period of three to four weeks during each sampling period.
Each block shall be scraped and analyzed for chlorophyll a using Standard Method 1002G or an equivalent approved by the Secretary. Results for each block shall be reported in terms of mg/m.
Data shall be analyzed for significant differences between stations using the Mann-Whitney U test procedure. For comparing 3 or more stations, the Kruskal-Wallis test procedure shall be used. Both tests shall use P [less than or equal] 0.001 (two-tailed).
The Pinkham-Pearson Coefficient of Similarity (PPCS) as described by Carlos F.
The PPCS is calculated as follows:
Where:
k = the number of comparisons between stations
xi = the number of individuals in taxon i
a,b = site a, site b
Examination of data on file at the Department of Environmental Conservation as well as from the general scientific literature suggest the following conclusions:
The biotic index to be used in this analysis is the Hilsenhoff Biotic Index (BI) (Hilsenhoff, 1982) with specific modifications made by the Secretary for the aquatic macroinvertebrate fauna of Vermont. The BI uses the concept of indicator organisms.
Each taxon is assigned a tolerance value based primarily on that specific organism's response to nutrient/ organic enrichment. As with the PPCS, the BI is an integrating index which uses information concerning both the relative abundance and organic pollution tolerance of individual taxa. The evaluation involves the stepwise analysis of each taxa, relating its pollution tolerance to its relative abundance in the community. Data on file at the Agency as well as the literature indicate that the BI is a highly sensitive and reliable index of nutrient/organic enrichment.
The following formula is used to calculate the BI:
Where:
N = the total number of individuals in the sample
m = the number of individuals in taxa i
ti = the tolerance value assigned taxa i
Data requirements for calculating the Biotic Index are the same as for PPCS calculations, with the following exceptions:
BI Value | Water Quality Rating |
BI < 1.5 | Excellent, undisturbed |
1.5 - 2. | Very good, minor change |
2.0 - 2.75 | Good, moderate change |
2.75 - 3.5 | Fair, major change |
BI | Poor, highly degraded |
Mayflies, stoneflies, and caddisflies make up a major proportion of the macroinvertebrate communities in Vermont's natural, undisturbed streams and these three orders of insects are relatively more sensitive to pollution and therefore respond to pollution in a relatively predictable manner. Changes measured in the taxa richness provide a reliable indication of changes to the taxonomic integrity of the aquatic biota. EPT taxa richness is defined here as the mean number of taxa from the orders Ephemeroptera, Plecoptera, and Trichoptera present at a site.
The EPT is calculated as follows:
Where: EPT i = the number of EPT taxa from replicate i
N = number of replicates
Data requirements are the same as for the PPCS.
Based on analysis of data on file with the Secretary as well as data in the literature, the following conclusions appear to be true:
Calculation of changes in the relative abundance of aquatic macroinvertebrates provides a means of evaluating changes in gross primary and secondary biologic production.
Relative abundance is defined here as the mean number of organisms per replicate from a sampling area and is calculated as follows:
Where: RA = Relative Abundance
N = number of replicates
T i = number of individuals in replicate i
Data requirements are the same as for the PPCS.
Telephone: 610-832-9585
100 Foot of Johns Street
Lowell, Massachusetts 01852
For copies of:
Guides For The Design Of Wastewater Treatment Works, 1998 Ed. New England Interstate Environmental Training Center
2 Fort Road
South Portland, Maine 04106
Telephone: 207-767-2539
Quincy, Massachusetts 02269-9101
Telephone: 800-344-3555
617 -770-3000
*The National Electrical Code is a Registered Trademark of the National Fire Protection Association, Inc. of Quincy Mass.
1300 North 1 [th ] Street
Suite 1847
Rosslyn, Virginia 22209
Telephone: 703-841-3200
Publications available through Global Engineering Documents
Telephone: 800-854-7179
www. global.ihs.org
P. O. Box 7126
Albany, NY 12224
Telephone: 518-439-7286
www. hes.org
Source for: Recommended Standards of Sewage Works, 1997 Edition
12-003 Code Vt. R. 12-033-003-X
January 31, 1990 Secretary of State Rule Log #90-03
AMENDED:
February 29, 1996 Secretary of State Rule Log #96-17; April 30, 2003 Secretary of State Rule Log #03-09; April 12, 2019 Secretary of State Rule Log #19-018
STATUTORY AUTHORITY:
10 V.S.A. §§ 905b, 1250, 1251a, 1259, 1263, 1390 to 1394