Current through Bulletin 2024-23, December 1, 2024
The State Park Access Highways Improvement Program is administered under all State Statutes. The following rules also apply.
(1) The Commission sets priorities for program monies.(2) The Commission uses the Joint Highway Committee to help in the project selection process.(3) Projects are selected annually unless an emergency arises.(4) Local Authorities shall follow the procedures of Section 72-6-107.(5) The Local Authority provides at least 50% of the cost of each project in matching funds.(6) The Local Authority agrees to use the funds within three years. The local authority repays all unused funds to UDOT.(7) The Local Authority certifies completion of the project and compliance with these rules to UDOT.Utah Admin. Code R926-5-4