Utah Admin. Code 746-312-7

Current through Bulletin 2024-23, December 1, 2024
Section R746-312-7 - Level 1 and Level 2 Interconnection Review Screens
(1) The public utility shall perform its review of Level 1 and Level 2 interconnection requests using the screens set forth in Subsection R746-312-7(9) as applicable.
(2) A generating facility's point of common coupling must be on a portion of the public utility's distribution system that is under the interconnection jurisdiction of the commission and must not be on a transmission line.
(3) For interconnection of a proposed generating facility to a radial distribution circuit, the aggregate generation on the distribution circuit, including the proposed generating facility, must not exceed 15% of the distribution circuit's total highest annual peak load, as measured at the substation. For Subsection R746-312-7(3), annual peak load will be based on measurements taken over the 60 months before the submittal of the application, measured for the circuit at the nearest applicable substation.
(4) The proposed generating facility, in aggregation with other generation on the distribution circuit to which the proposed generating facility will interconnect, must not contribute more than 10% to the distribution circuit's maximum fault current at the point on the high voltage, or primary, level nearest the proposed point of common coupling.
(5) If the proposed generating facility is to be connected to a single-phase shared secondary, the aggregate generation capacity connected to the shared secondary, including the proposed generating facility, must not exceed 20 kilowatts.
(6) If a proposed single-phase generating facility is to be connected to a transformer center tap neutral of a 240-volt service, the addition of the proposed generating facility must not create a current imbalance between the two sides of the 240-volt service of more than 20% of nameplate rating of the service transformer.
(7) No construction of facilities by the public utility on its own system shall be required to accommodate the generating facility.
(8) The aggregate generation capacity on the distribution circuit to which the proposed generating facility will interconnect, including the capacity of the proposed generating facility, must not cause any distribution protective equipment, including substation breakers, fuse cutouts, and line reclosers, or customer equipment on the electric distribution system, to exceed 90% of the short circuit interrupting capability of the equipment. In addition, a proposed generating facility must not be connected to a circuit that already exceeds 90% of the circuit's short circuit interrupting capability, before interconnection of the facility.
(9) Interconnection Type Screen:
(a) For a proposed generating facility connecting to a three-phase, three wire primary public utility distribution line, a three-phase or single-phase generator must be connected phase-to-phase.
(b) For a proposed generating facility connecting to a three-phase, four wire primary public utility distribution line, a three-phase or single-phase generator must be connected line-to-neutral and must be effectively grounded.
(10) If there are known or posted transient stability limitations to generating units located in the general electrical vicinity of the proposed point of common coupling, including within three or four transmission voltage level busses, the aggregate generation capacity, including the proposed generating facility, connected to the distribution low voltage side of the substation transformer feeding the distribution circuit containing the point of common coupling may not exceed ten megawatts.
(11) If a proposed generating facility's point of common coupling is on a spot network, the proposed generating facility must use an inverter-based equipment package and, together with the aggregated other inverter-based generation, must not exceed the smaller of 5% of a spot network's maximum load or 50 kilowatts.

Utah Admin. Code R746-312-7

Amended by Utah State Bulletin Number 2017-2, effective 12/22/2016
Amended by Utah State Bulletin Number 2024-08, effective 4/9/2024