Section R652-100-1000 - Plans of Operation1. Prior to the commencement of any activity authorized by a materials permit the permittee shall be required to submit, for the director's approval, a plan of operations which shall include the following: (a) A map or plat showing i) the location and sequence of areas from which material is to be excavated; ii) the location of any processing or stationary equipment or improvements which will be placed on the premises; iii) transportation and access routes across the premises and adjacent properties; iv) the location of any fuel storage tanks; and, v) the location of stockpile areas.(b) Elevation drawings of the premises before and after the excavation of materials.(c) Reclamation plans prepared by any governmental agency, or if not acceptable to the director, as required by the director.Utah Admin. Code R652-100-1000