Utah Admin. Code 647-4-101

Current through Bulletin 2024-23, December 1, 2024
Section R647-4-101 - Filing Requirements and Review Procedures

Prior to commencement of operations, a Notice of Intention to Commence Large Mining Operations (FORM MR-LMO) containing all the required information must be filed with and approved by the Division and the Division shall have approved the form and amount of reclamation surety.

1. Within 30 days after receipt of a Notice of Intention, or within 30 days after receipt of any subsequent submittal, the Division will complete its review and notify the operator in writing:
1.11. That the notice of intention is complete; or
1.12. That the notice of intention is incomplete, and that additional information as identified by the Division will be required.
2. Within 30 days after receipt of the notice of intention or within 30 days following the last action of the operator or Division on the notice of intention, the Division shall reach a tentative decision with respect to the approval or denial of the notice of intention.

Notice of the tentative decision will then be published in accordance with Rule R647-4-116.

3. Division approval of the notice of intention and execution of the Reclamation Contract (FORM MR-RC) by the operator shall bind the Division and the operator in accordance with the Act and implementing regulations; and, shall enable the operator to conduct mining and reclamation activities in accordance therewith.
4. The operator must notify the Division within 30 days of beginning mining operations.
5. A permittee's retention of an approved notice of intention shall require the paying of permit fees as authorized by the Utah Legislature. The procedures for paying the permit fees are as follows:
5.11. The Division shall notify the operators of record annually of the amount of permit fees authorized by the Utah Legislature for the following notices of intention.
5.11.11. Large Mining Operations (less than 50 acres) (fees calculated on the disturbed acreage permitted/bonded).
5.11.12. Large Mining Operations (greater than 50 acres) (fees calculated on the disturbed acreage permitted/bonded).
5.12. Fees are due annually by the deadline in R647-4-121 for reports.
5.13. A permittee may avoid payment of the fee by complying with the following requirements:
5.13.11. A permittee will notify the Division of a desire to close out a notice of intention by checking the appropriate box of the permit fees billing form.
5.13.12. The permittee will then arrange with the Division for an onsite inspection of the site to assure that all required reclamation has been performed. If an inspection reveals that an area is not yet suitably reclaimed, then a new billing notice will be issued and the permittee will be given 30 days from the date of the onsite inspection to pay the fee.

Utah Admin. Code R647-4-101

Amended by Utah State Bulletin Number 2020-04, effective 2/10/2020