Current through Bulletin No. 2024-21, November 1, 2024
Section R647-3-115 - Revisions1. Small mining operators are required to submit a revision to the complete notice of intention when a significant change(s) in the small mining operation occurs. A revision can be made by submitting a revised FORM MR-SMO (or similar form) and indicating the portion(s) of the operation which is being revised.2. Division approval of a revision of small mining operations is not required but the operational change may not be implemented until the Division determines that the revised NOI is complete.3. In the event the Division or the operator determine at the time a revision is submitted that the amount of the current surety does not accurately reflect the potential cost to complete reclamation at any point in time during the revised small mining operations, the Division may undertake a recalculation of the surety amount as provided in R647-3-111.3. If the recalculated amount is greater than the amount of the existing surety, the revised operations may not be implemented until a revised surety is approved by the Division.4. If the acreage within an approved small mining operation is later annexed into an incorporated area of a county, the permit may continue as a small mining operation. If the operator of such small mining operation subsequently proposes an increase of the disturbed acres, the current definitions for small or large mining operations would apply as appropriate.Utah Admin. Code R647-3-115
Amended by Utah State Bulletin Number 2020-04, effective 2/10/2020