Utah Admin. Code 317-801-6

Current through Bulletin 2024-20, October 15, 2024
Section R317-801-6 - Certification, Submission and Implementation Requirements
6.1 Timeline for Notice, SSMP, and Certification. The permittee shall certify to DWQ that a SSMP is in place that is in compliance with the USMP by submitting a notice to DWQ within the time frames identified in the following time schedule:

Table 1. Timeframe for Implementation.

Task

Completion Dates by Population

>50,000 population

15,001 to 50,000 population

3,501 to 15,000 population

3,500 and Less population

Notice of Intent to be covered by General Permit

4 - 6 Months after effective date of rule

Completion of SSMP (excluding SECAP)

24 months after effective date

30 months after effective date

36 months after effective date

42 months after effective date

Completion of SECAP when required

36 months after effective date

42 months after effective date

48 months after effective date

60 months after effective date

6.2 Significant Modifications. Significant modification of the SSMP must be public noticed by the permittee and approved by the permittee's governing body at a public meeting. A new notice certifying the revised SSMP is in place shall be sent to DWQ.
6.4 Incomplete Reports. If a permittee becomes aware that it failed to submit required information in any notice or report, the permittee shall promptly amend the notice or report.
6.5 Certification of Notices and Reports. All notices and reports submitted to DWQ shall be signed and certified as required in R317-8-3.4.

Utah Admin. Code R317-801-6