Section R307-415-5a - Permit Applications: Duty to Apply

For each Part 70 source, the owner or operator shall submit a timely and complete permit application. A pre-application conference may be held at the request of a Part 70 source or the director to assist a source in submitting a complete application.

(1) Timely application.
(a) Except as provided in the transition plan under (3) below, a timely application for a source applying for an operating permit for the first time is one that is submitted within 12 months after the source becomes subject to the permit program.
(b) Except as provided in the transition plan under (3) below, any Part 70 source required to meet the requirements under Section 112(g) of the Act, Hazardous Air Pollutant Modifications, or required to receive an approval order to construct a new source or modify an existing source under R307-401, shall file a complete application to obtain an operating permit or permit revision within 12 months after commencing operation of the newly constructed or modified source. Where an existing operating permit would prohibit such construction or change in operation, the source must obtain a permit revision before commencing operation.
(c) For purposes of permit renewal, a timely application is one that is submitted by the renewal date established in the permit. The director shall establish a renewal date for each permit that is at least six months and not greater than 18 months prior to the date of permit expiration. A source may submit a permit application early for any reason, including timing of other application requirements.
(2) Complete application.
(a) To be deemed complete, an application must provide all information sufficient to evaluate the subject source and its application and to determine all applicable requirements pursuant to R307-415-5 c. Applications for permit revision need supply such information only if it is related to the proposed change. A responsible official shall certify the submitted information consistent with R307-415-5d.
(b) Unless the director notifies the source in writing within 60 days of receipt of the application that an application is not complete, such application shall be deemed to be complete. A completeness determination shall not be required for minor permit modifications. If, while processing an application that has been determined or deemed to be complete, the director determines that additional information is necessary to evaluate or take final action on that application, the director may request such information in writing and set a reasonable deadline for a response. The source's ability to operate without a permit, as set forth in R307-415-7 b(2), shall be in effect from the date the application is determined or deemed to be complete until the final permit is issued, provided that the applicant submits any requested additional information by the deadline specified in writing by the director.
(3) Transition Plan. A timely application under the transition plan is an application that is submitted according to the following schedule:
(a) All Title IV affected sources shall submit an operating permit application as well as an acid rain permit application in accordance with the date required by 40 CFR Part 72 effective April 11, 1995, Subpart C-Acid Rain Permit Applications;
(b) All major Part 70 sources operating as of July 10, 1995, except those described in (a) above, and all solid waste incineration units operating as of July 10, 1995, that are required to obtain an operating permit pursuant to 42 U.S.C. Sec. 7429(e) shall submit a permit application by October 10, 1995.
(c) Area sources.
(i) Except as provided in (c)(ii) and (c)(iii) below, each Part 70 source that is not a major source, a Title IV affected source, or a solid waste incineration unit required to obtain a permit pursuant to section 129(e) (42 U.S.C. 7429), is deferred from the obligation to submit an application until 12 months after the Administrator completes a rulemaking to determine how the program should be structured for area sources and the appropriateness of any permanent exemptions in addition to those provided in R307-415-4(2).
(ii) General Permits.
(A) The director shall develop general permits and application forms for area source categories.
(B) After a general permit has been issued for a source category, the director shall establish a due date for permit applications from all area sources in that source category.
(C) The director shall provide at least six months notice that the application is due for a source category.
(iii) Regulation-specific Requirements.
(A) If a regulation promulgated under Section 111 or 112 (42 U.S.C. 7411 or 7412) requires an area source category to submit an application for a Part 70 permit, each area source covered by the requirement must submit an application in accordance with the regulation.
(d) Extensions. The owner or operator of any Part 70 source may petition the director for an extension of the application due date for good cause. The due date for major Part 70 sources shall not be extended beyond July 10, 1996. The due date for an area source shall not be extended beyond twelve months after the due date in (c)(i) above.
(e) Application shield. If a source submits a timely and complete application under this transition plan, the application shield under R307-415-7 b(2) shall apply to the source. If a source submits a timely application and is making sufficient progress toward correcting an application determined to be incomplete, the director may extend the application shield under R307-415-7b(2) to the source when the application is determined complete. The application shield shall not be extended to any major source that has not submitted a complete application by July 10, 1996, or to any area source that has not submitted a complete application within twelve months after the due date in (c)(i) above.
(4) Confidential information. Claims of confidentiality on information submitted to EPA may be made pursuant to applicable federal requirements. Claims of confidentiality on information submitted to the Department shall be made and governed according to Section 19-1-306. In the case where a source has submitted information to the Department under a claim of confidentiality that also must be submitted to the EPA, the director shall either submit the information to the EPA under Section 19-1-306, or require the source to submit a copy of such information directly to EPA.
(5) Late applications. An application submitted after the deadlines established in R307-415-5 a shall be accepted for processing, but shall not be considered a timely application. Submitting an application shall not relieve a source of any enforcement actions resulting from submitting a late application.