Current through Bulletin No. 2024-21, November 1, 2024
Section R23-5-8 - Funding of Project Reserve(1) After all major construction contracts for a project have been awarded, and after setting aside adequate reserves for any remaining construction work which was not included in the construction contracts, any remaining balance of appropriated funds in the construction budget shall be transferred to the project reserve.(2) Upon completion of the project, any residual balance of appropriated funds in any budget category shall be transferred to the project reserve; however, if the residual balance is the result of a reduction in a contract balance which had previously been funded from the statewide contingency reserve, the residual balance shall be transferred instead to the statewide contingency reserve.Amended by Utah State Bulletin Number 2018-4, effective 1/23/2018Amended by Utah State Bulletin Number 2023-04, effective 2/8/2023