Section 331.225 - Geophysical or Drilling Log

If an existing well is to be converted to an injection well, monitoring well, or production well, the commission may require the applicant to provide a geophysical log or a drilling log of the existing well.

30 Tex. Admin. Code § 331.225

The provisions of this §331.225 adopted to be effective March 12, 2009, 34 TexReg 1638