30 Tex. Admin. Code § 295.159

Current through Reg. 49, No. 45; November 8, 2024
Section 295.159 - Notice of Extension of Time to Commence or Complete Construction
(a) If the new date of proposed commencement of construction is more than four years from the date of issuance of the permit, or if the new proposed completion time is more than five years from the date of completion required in the original permit, notice of an application for extension of time shall be mailed and published as required by the Texas Water Code, § 11.132 and § 11.143, and § 295.151 of this title (relating to Notice of Application and Commission Action), § 295.152 of this title (relating to Notice by Publication), and § 295.153 of this title (relating to Notice by Mail). The chief clerk shall mail notice of the public hearing to the same persons to whom notice of the application for the permit was mailed. The applicant shall be required to publish notice of the hearing in the same manner in which an applicant for a water use permit is required to publish notice of an application. No other notice is required.
(b) The notice of any application for an extension of time to commence or complete construction must provide that the commission shall also consider whether the appropriation shall be forfeited for failure by the applicant to demonstrate sufficient due diligence and justification for delay.
(c) This section does not apply to a permit for construction of a reservoir designed for storage of more than 50,000 acre-feet of water. No notice shall be required for an extension of time to commence or complete construction of a reservoir designed for storage of more than 50,000 acre-feet of water.

30 Tex. Admin. Code § 295.159

The provisions of this §295.159 adopted to be effective May 28, 1986, 11 TexReg 2326; amended to be effective January 30, 1992, 17 TexReg 407; Amended by Texas Register, Volume 45, Number 19, May 8, 2020, TexReg 3101, eff. 5/14/2020