30 Tex. Admin. Code § 117.3045

Current through Reg. 49, No. 44; November 1, 2024
Section 117.3045 - Notification, Recordkeeping, and Reporting Requirements
(a) Startup and shutdown records. For units subject to the startup and/or shutdown provisions of § 101.222 of this title (relating to Demonstrations), hourly records must be made of startup and/or shutdown events and maintained for a period of at least two years. Records must be available for inspection by the executive director, United States Environmental Protection Agency, and any local air pollution control agency having jurisdiction upon request. These records must include, but are not limited to: type of fuel burned; quantity of each type fuel burned; gross and net energy production in megawatt-hours (MW-hr); and the date, time, and duration of the event.
(b) Notification. The owner or operator of a unit subject to the emission specifications of this division (relating to Utility Electric Generation in East and Central Texas) shall submit notification to the executive director as follows:
(1) verbal notification of the date of any initial demonstration of compliance testing conducted under § 117.3035 of this title (relating to Initial Demonstration of Compliance) at least 15 days prior to such date followed by written notification within 15 days after testing is completed; and
(2) verbal notification of the date of any continuous emissions monitoring systems (CEMS) or predictive emissions monitoring systems (PEMS) performance evaluation conducted under § 117.3040 of this title (relating to Continuous Demonstration of Compliance) at least 15 days prior to such date followed by written notification within 15 days after testing is completed.
(c) Reporting of test results. The owner or operator of an affected unit shall furnish the executive director and any local air pollution control agency having jurisdiction a copy of any initial demonstration of compliance testing conducted under § 117.3035 of this title or any CEMS or PEMS performance evaluation conducted under § 117.3040 of this title:
(1) within 60 days after completion of such testing or evaluation; and
(2) not later than the appropriate compliance schedule specified in § 117.9300 of this title (relating to Compliance Schedule for Utility Electric Generation in East and Central Texas).
(d) Annual reports. The owner or operator of a unit required to install a CEMS, PEMS, or steam-to-fuel or water-to-fuel ratio monitoring system under § 117.3040 of this title shall report in writing to the executive director on an annual basis any exceedance of the applicable emission specifications in this division and the monitoring system performance. All reports must be postmarked or received by January 31 following the end of each calendar year. Written reports must include the following information:
(1) the magnitude of excess emissions computed in accordance with 40 Code of Federal Regulations §60.13(h), any conversion factors used, the date and time of commencement and completion of each time period of excess emissions, and the unit operating time during the reporting period. For stationary gas turbines using steam-to-fuel or water-to-fuel ratio monitoring to demonstrate compliance in accordance with § 117.3040 of this title, excess emissions are computed as each one-hour period that the hourly steam-to-fuel or water-to-fuel ratio is less than the ratio determined to result in compliance during the initial demonstration of compliance test required by § 117.3035 of this title;
(2) specific identification of each period of excess emissions that occurs during startups, shutdowns, and malfunctions of the affected unit. The nature and cause of any malfunction (if known) and the corrective action taken or preventative measures adopted;
(3) the date and time identifying each period that the continuous monitoring system was inoperative, except for zero and span checks and the nature of the system repairs or adjustments;
(4) when no excess emissions have occurred or the continuous monitoring system has not been inoperative, repaired, or adjusted, such information must be stated in the report; and
(5) if the total duration of excess emissions for the reporting period is less than 1.0% of the total unit operating time for the reporting period and the CEMS, PEMS, or steam-to-fuel or water-to-fuel ratio monitoring system downtime for the reporting period is less than 5.0% of the total unit operating time for the reporting period, only a summary report form (as outlined in the latest edition of the commission's Guidance for Preparation of Summary, Excess Emission, and Continuous Monitoring System Reports) must be submitted, unless otherwise requested by the executive director. If the total duration of excess emissions for the reporting period is greater than or equal to 1.0% of the total operating time for the reporting period or the CEMS or steam-to-fuel or water-to-fuel ratio monitoring system downtime for the reporting period is greater than or equal to 5.0% of the total operating time for the reporting period, a summary report and an excess emission report must both be submitted.
(e) Recordkeeping. The owner or operator of a unit subject to the requirements of this division shall maintain records of the data specified in this subsection. Records must be kept for a period of at least five years and made available for inspection by the executive director, United States Environmental Protection Agency, or local air pollution control agencies having jurisdiction upon request. Operating records for each unit must be recorded and maintained at a frequency equal to the applicable emission specification averaging period, or for units claimed exempt from the emission specifications based on low annual capacity factor, monthly. Records must include:
(1) emission rates in units of the applicable standards;
(2) gross energy production in MW-hr (not applicable to auxiliary steam boilers);
(3) quantity and type of fuel burned;
(4) the injection rate of reactant chemicals (if applicable); and
(5) emission monitoring data in accordance with § 117.3040 of this title, including:
(A) the date, time, and duration of any malfunction in the operation of the monitoring system, except for zero and span checks, if applicable, and a description of system repairs and adjustments undertaken during each period;
(B) the results of initial certification testing, evaluations, calibrations, checks, adjustments, and maintenance of CEMS, PEMS, or operating parameter monitoring systems; and
(C) actual emissions or operating parameter measurements, as applicable;
(6) the results of performance testing, including initial demonstration of compliance testing conducted in accordance with § 117.3035 of this title; and
(7) records of hours of operation.

30 Tex. Admin. Code § 117.3045

The provisions of this §117.3045 adopted to be effective June 14, 2007, 32 TexReg 3206