Current through Reg. 49, No. 52; December 27, 2024
Section 74.78 - Responsibilities of the Contractor - Compliance with Plan Review(a) The contractor must comply with the requirements for plan review as set forth in this chapter.(b) The contractor must provide the inspector a copy of the approved application and plans and, upon completion of the inspection, leave a copy of the approved application and plans in the machine room, machine space, control room or control space.16 Tex. Admin. Code § 74.78
The provisions of this §74.78 adopted to be effective July 1, 2012, 37 TexReg 4590; amended to be effective November 15, 2013, 38 TexReg 7949