Tenn. Comp. R. & Regs. 1200-03-30-.05

Current through December 10, 2024
Section 1200-03-30-.05 - ACID RAIN PERMIT (40 CFR PART 72, SUBPART E)
(1) Contents. ( 40 CFR 72.50 )
(a) Each Acid Rain permit (including any draft or proposed Acid Rain permit) will contain the following elements:
1. All elements required for a complete Acid Rain permit application under paragraph 1200-3-30-.03(2), as approved or adjusted by the Technical Secretary;
2. The applicable Acid Rain emissions limitation for sulfur dioxide; and
3. The applicable Acid Rain emissions limitation for nitrogen oxides.
(b) Each Acid Rain permit is deemed to incorporate the definitions of terms under paragraph 1200-3-30-.01(1).
(2) Permit shield. ( 40 CFR 72.51 )

Each affected unit operated in accordance with the Acid Rain permit that governs the unit and that was issued in compliance with title IV of the Act, as provided in Rule 1200-3-30-.01 through Rule 1200-3-30-.08, 40 CFR parts 72, 73, 75, 77, and 78, and the regulations implementing section 407 of the Act, shall be deemed to be operating in compliance with the Acid Rain Program, except as provided in part 1200-3-30-.01(6)(g) 6.

Tenn. Comp. R. & Regs. 1200-03-30-.05

Original rule filed June 30, 1994; effective September 15, 1994.

Authority: T.C.A. §§ 668-201-105 and 4-5-202.