Tenn. Comp. R. & Regs. 1200-03-16-.59

Current through December 10, 2024
Section 1200-03-16-.59 - INDUSTRIAL COMMERCIAL-INSTITUTIONAL STEAM GENERATING UNITS
(1) Applicability and Definition of Affected Facility
(a) The affected facility to which this rule applies is each industrial-commercial-institutional steam generating unit for which construction, modification, or reconstruction is commenced after November 6, 1988 and which has a heat input capacity from fuels combusted in the steam generating unit of more than 29 MW (100 million Btu/hour).
(b) Reserved
(c) Reserved
(d) Reserved
(e) Reserved
(f) Reserved
(g) Any affected facility meeting the applicability requirements of subparagraph (a) of this paragraph commencing construction, modification, or reconstruction after November 6, 1988 is not subject to Rule 1200-03-16-.02.
(2) Reserved

Tenn. Comp. R. & Regs. 1200-03-16-.59

Original rule filed September 21, 1988; effective November 6, 1988. Amendments filed January 21, 2009; effective April 6, 2009. Amendments filed March 7, 2016; effective 6/5/2016.

Authority: T.C.A. §§ 68-25-105, 68-201-101 et seq., 4-5-201 et seq., and 4-5-202.