1. Disposal Facility | |
(i) Class I | |
Hydrogeologic | $ 4,000.00 |
Design and Construction Plans | $ 6,000.00 |
(ii) Class II | |
Hydrogeologic | $ 4,000.00 |
Design and Construction Plans | $ 6,000.00 |
(iii) Class III | $ 3,000.00 |
2. Processing Facility | $ 1,000.00 |
3. Major Modifications | $ 2,000.00 |
4. Special Waste Evaluation | $ ..... 300.00 |
5. Transfer Station | $ 500.00 |
6. Transfer of Ownership | $ 1,000.00 |
7. Special Waste Recertification | $ ..... 150.00 |
(i)Class I (Tons/Year) | |
(I) Greater than 50,000 | $15,000.00 |
(II) 25,000 to 50,000 | $10,000.00 |
(III) Less than 25,000 | $ 5,000.00 |
(IV) Zero Tons (Post Closure Period) | $ 1,000.00 |
(ii)Class II (Tons/Year) | |
(I) Greater than 1,000 T | $10,000.00 |
(II) Less than 1,000 T | $ 4,000.00 |
(iii) Class III (Tons/Year) | |
(I) Greater than 10,000 | $ 4,000.00 |
(II) Less than 10,000 | $ 3,000.00 |
(iv) Class IV (Tons/Year) | |
(I) Greater than 10,000 | $ 4,000.00 |
(II) Less than 10,000 | $ 3,000.00 |
2. Processing Facilities | $ 3,000.00 |
3. Transfer Station | $ 1,500.00 |
4. Coal Ash Fill Area | $ 3,000.00 |
5. Land Application Facility | $ 100.00 |
1. Hydrogeologic Report for Disposal Facilities | 30 days |
2. Design and Construction Plans for Disposal & Compost Facilities | 45 days |
(i) Class I | 270 days |
(ii) Class II | 270 days |
(iii) Class III | 240 days |
2. Processing Facility | |
Permit By Rule | 90 days |
Compost Facility | 120 days |
3. Major Modification | |
(i) Regulatory Requirement | 180 days |
(ii) Application | 180 days |
(I) Plans Only | 240 days |
(II) Hydrogeologic | 270 days |
4. Waste Evaluation | 30 days |
Tenn. Comp. R. & Regs. 1200-01-07-.07
Authority: T.C.A. §§ 4-5-201, et seq., 68-203-103(a)(1), 68-203-103(b)(3), 68-211-102(a), 68-211-105(b), 68-211-105(c), 68-211-106(a)(1), 68-211-107(a), 68-211-111(d), 68-211-111(d)(1), 68-211-111(d)(2), 68-211-851(a), 68-211-852, 68-211-853, and 68-211-861.