If the verifying analysis indicates that an excursion has occurred, the operator shall submit to the secretary for review and approval a remedial action plan and a ground water analysis report to include the following:
The operator shall report every two weeks. All reports shall be mailed to the secretary, postmarked within two days of the end of each report period. The first report period shall begin the day the presence of a control parameter exceeding its upper limit value in a monitor well is verified. The operator shall continue to make remedial action reports until cleanup is accomplished.
Following review by the secretary, the operator shall use methods judged necessary and prudent to define the extent of the excursion and to cleanup recovery fluids in an expeditious manner.
S.D. Admin. R. 74:55:01:53
General Authority: SDCL 34A-2-93(15).