S.D. Admin. R. 74:51:01:64.03

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:51:01:64.03 - Contents of public notice for certification of compliance with water quality standards

At a minimum, the public notice required in §§ 74:51:01:64 to 74:51:01:64.02, inclusive, must include the following:

(1) A brief description of the proposed activity and a summary of the application information required in the application;
(2) A period of time, at least 15 days from the date of mailing, within which interested parties may express their views concerning the permit application; and
(3) A statement that any person may request, in writing, within the comment period specified in the notice, that a public hearing pursuant to chapter 74:50:02 be held to consider the application. Requests for public hearings must state the reasons for holding a public hearing.

S.D. Admin. R. 74:51:01:64.03

14 SDR 86, effective 12/24/1987; 19 SDR 111, effective 1/31/1993; 21 SDR 18, effective 8/8/1994; transferred from § 74:51:01:64, 24 SDR 10, effective 7/20/1997; 31 SDR 29, effective 9/13/2004; 41 SDR 109, effective 1/12/2015; 47 SDR 110, effective 4/27/2021

General Authority: SDCL 34A-2-11, 34A-2-33, 34A-2-34, 34A-2-93.

Law Implemented: SDCL 34A-2-33, 34A-2-34.