S.D. Admin. R. 74:37:01:07.01

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:37:01:07.01 - Flat fee for asphalt plants

The annual flat fee for an existing single asphalt plant with a general permit is $333. The administrative fee in § 74:37:01:04, the annual air emission fee in § 74:37:01:05, and the annual operational report in § 74:37:01:06 do not apply to any single asphalt plant with a general permit.

S.D. Admin. R. 74:37:01:07.01

20 SDR 218, effective 7/1/1994; 36 SDR 208, effective 6/28/2010; 44 SDR 95, effective 12/5/2017; 45 SDR 153, effective 6/24/2019

General Authority: SDCL 34A-1-58.

Law Implemented: SDCL 34A-1-58.