The owner or operator of a new major source, modification to a major source, or a BART-eligible source that emits any air pollutant which may reasonably be anticipated to contribute to adverse impact on visibility in any mandatory Class I federal area shall install, operate, and maintain the controls established in a visibility impact analysis or BART determination. The owner or operator of a new major source or modification to a major source must install and operate the controls established in a visibility impact analysis at initial startup. The owner or operator of a BART-eligible source required to install BART must install, operate, and demonstrate compliance with BART as expeditiously as practicable, but no later than five years from EPA's approval of the state implementation plan for regional haze.
S.D. Admin. R. 74:36:21:07
General Authority: SDCL 34A-1-6.
Law Implemented: SDCL 34A-1-6.