Section 74:32:05:08.02 - Assessment workplan - Contents

An assessment workplan must contain the following provisions:

(1) A brief summary of the nature of the work to be completed and the sequence of planned activities;
(2) A proposed time schedule for commencing and completing major activities, including the release investigation report;
(3) A written discussion of the rationale for selecting the number and placement of monitoring wells and soil borings;
(4) A written discussion of the rationale for selecting which water and soil samples will be retained for laboratory analysis;
(5) The names of the constituents for which a laboratory analysis is to be performed;
(6) The method used for determining the direction of local groundwater flow;
(7) A brief summary of the quality assurance and quality control plan which will be followed during the release investigation;
(8) A description of all computer models that may be used in the pathway and fate analysis, costs analysis of remedial alternatives, design of remedial alternatives, or risk assessment; and
(9) Other provisions the director or department determine to be necessary for the assessment.