Section 74:32:05:08.02 - Assessment workplan - ContentsAn assessment workplan must contain the following provisions:
(1) A brief summary of the nature of the work to be completed and the sequence of planned activities;(2) A proposed time schedule for commencing and completing major activities, including the release investigation report;(3) A written discussion of the rationale for selecting the number and placement of monitoring wells and soil borings;(4) A written discussion of the rationale for selecting which water and soil samples will be retained for laboratory analysis;(5) The names of the constituents for which a laboratory analysis is to be performed;(6) The method used for determining the direction of local groundwater flow;(7) A brief summary of the quality assurance and quality control plan which will be followed during the release investigation;(8) A description of all computer models that may be used in the pathway and fate analysis, costs analysis of remedial alternatives, design of remedial alternatives, or risk assessment; and(9) Other provisions the director or department determine to be necessary for the assessment.S.D. Admin. R. 74:32:05:08.02
17 SDR 94, effective 1/6/1991; 23 SDR 220, effective 6/25/1997.General Authority: SDCL 34A-13-5.
Law Implemented: SDCL 34A-13-5, 34A-13-15, 34A-13-31.