S.D. Admin. R. 74:31:02:01

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:31:02:01 - Levels of responsibility

Levels of responsibility. The levels of responsibility or disciplines of persons who work with asbestos abatement projects are as follows:

(1) Inspector;
(2) Management planner;
(3) Abatement project designer;
(4) Asbestos abatement supervisor or contractor; and
(5) Asbestos abatement worker.

S.D. Admin. R. 74:31:02:01

14 SDR 164, effective 6/5/1988; 18 SDR 95, effective 12/2/1991.

General Authority: SDCL 34-44-3, 34-44-4.

Law Implemented: SDCL 34-44-3, 34-44-4.