S.D. Admin. R. 74:29:11:30

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:29:11:30 - Production area operational monitoring requirements

The monitoring plan included in the permit shall describe the procedures for operational monitoring of the quantity and quality of mining solution and ground water in the production area and shall, at a minimum, include provisions for:

(1) The analysis of the physical and chemical characteristics of the injected fluid, with sufficient frequency, and at least monthly, to yield representative data. Manifold monitoring may be used in cases of facilities consisting of more than one injection well operating with a common manifold. Separate monitoring systems for each well are not required provided the operator demonstrates to the department that manifold monitoring is comparable to individual well monitoring;
(2) Monitoring injection pressure and either flow rate or volume twice a month, or metering and recording daily injected and produced fluid volumes;
(3) Monitoring the fluid level in the injection zone twice a month;
(4) Monitoring ground water quality, including the control parameters, and fluid levels in monitoring wells completed above and below the production zone a minimum of every month; and
(5) A minimum of quarterly monitoring of department specified wells within one-quarter mile of the production site to detect migration of recovery fluids from the production zone.

S.D. Admin. R. 74:29:11:30

33 SDR 160, effective 4/17/2007.

General Authority: SDCL 45-6B-81.

Law Implemented: SDCL 45-6B-41.