Before initiation of land application of solution, the operator must submit a written plan for operational monitoring of the land application area to the department and the department of game, fish and parks for review and approval. The plan must include the following:
(1) Methods for soil and soil water monitoring and sampling;(2) Vegetation sampling and analysis;(3) Soil characteristics and parameters to be monitored;(4) Proposed analytical techniques;(6) Criteria for determining if and when land application should be initiated or discontinued;(7) Surface and groundwater monitoring plans;(8) Maximum allowable metals accumulation values; and(9) A sampling and analytical quality assurance and quality control plan.S.D. Admin. R. 74:29:05:17
14 SDR 111, effective 3/3/1988.General Authority: SDCL 45-6B-81.
Law Implemented: SDCL 45-6B-39, 45-6B-41, 45-6B-44, 45-6B-45