Section 74:29:01:19 - Report required following issuance of uncontested permit

In accordance with SDCL 1-40-29, following the issuance of any uncontested permit under this chapter, the secretary shall give the board a report containing the following information:

(1) The notice of decision pursuant to § 74:29:01:18;
(2) The name, address, and telephone number of the operator;
(3) The legal description of the affected land;
(4) The mineral or minerals to be extracted;
(5) A narrative description of the permit or the summary document prepared pursuant to § 74:29:01:10;
(6) The proposed duration of the operation;
(7) The affected land acreage;
(8) The surface mining disturbed land acreage; and
(9) The postmining land use of the area.