S.D. Admin. R. 74:27:12:23

Current through Register Vol. 51, page 34, September 9, 2024
Section 74:27:12:23 - Construction notification

The applicant shall notify the secretary at least 30 days before the expected initiation of construction. In addition, the operator shall maintain "as built" drawings of the facility.

S.D. Admin. R. 74:27:12:23

17 SDR 8, effective 7/26/1990; 19 SDR 186, effective 6/10/1993.

General Authority: SDCL 34A-6-1.6.

Law Implemented: SDCL 34A-6-1.6.