Section 74:27:08:05 - Presubmission meetings

An applicant proposing to construct a new Type I or IIA facility shall schedule a presubmission meeting with the secretary at least 30 days before submittal of the Phase I application. Other applicants may schedule meetings with the secretary to discuss general and technical application requirements, including the site characterization required by chapter 74:27:12, in advance of permit application preparation.

S.D. Admin. R. 74:27:08:05

17 SDR 8, effective 7/26/1990; 19 SDR 186, effective 6/10/1993.

General Authority: SDCL 34A-6-1.6.