S.D. Admin. R. 74:21:02:37

Current through Register Vol. 51, page 56, November 4, 2024
Section 74:21:02:37 - Restricted certificates due to plant or system reclassifications

Within one year after a classification upgrading unrelated to a system or plant modification, the owner of a plant or system may request that its operator be granted a restricted certificate if the operator of the plant or system was certified so that the plant or system was in compliance with SDCL 34A-3 prior to its reclassification.

In considering the request, the secretary shall review the following:

(1) The magnitude of the change;
(2) The operator's training;
(3) The operator's past performance; and
(4) The recommendation of the board.

The secretary may grant or deny the request and shall notify the owner of the decision and the reasons therefor within 45 days. A restricted certificate granted pursuant to this section is valid only for the specified operator at the specified plant or system.

S.D. Admin. R. 74:21:02:37

6 SDR 49, effective 1/1/1981; 12 SDR 209, effective 7/7/1986; 13 SDR 129, 13 SDR 141, effective 7/1/1987; 27 SDR 53, effective 12/4/2000.

General Authority: SDCL 34A-3-24.

Law Implemented: SDCL 34A-3-3, 34A-3-4.