Any applicant requesting financial assistance for a wastewater treatment works or storm water project must prepare a facilities plan. A facilities plan is not required from an applicant requesting funding for other types of projects. The facilities plan shall at minimum provide the information contained in § 74:05:08:01(8). The applicant shall be notified of any deficiencies in the draft facilities plan submitted with the application. A completed facilities plan must be received by the department to initiate the environmental review process. The facilities plan is not considered complete until the following items are received:
S.D. Admin. R. 74:05:08:13.02
General Authority: SDCL 46A-1-60.3.
Law Implemented: SDCL 46A-1-60.1 to 46A-1-60.3.