S.D. Admin. R. 74:02:04:75

Current through Register Vol. 51, page 67, December 16, 2024
Section 74:02:04:75 - Variance

A well driller may request a variance from requirements of this chapter from the chief engineer. The chief engineer may grant a variance for a request that is reasonable in the chief engineer's judgment. The variance may be authorized by telephone with written authorization following by mail.

S.D. Admin. R. 74:02:04:75

SL 1975, ch 16, § 1; transferred from § 52:01:02:12, effective 7/1/1979; transferred from § 74:02:02:12, 12 SDR 50, effective 9/29/1985; 13 SDR 129, 13 SDR 141, effective 7/1/1987; 18 SDR 224, effective 7/16/1992.

General Authority: SDCL 46-2-5, 46-6-6.1, 46-6-9, 46-6-20, 46-6-27.

Law Implemented: SDCL 46-2-9, 46-6-6.1, 46-6-9, 46-6-10, 46-6-20, 46-6-27, 46-6-28.