If a well constructed using alternative construction techniques pursuant to §§ 74:02:04:35 and 74:02:04:36 and operated pursuant to written instructions provided by the well driller produces an increase in mud or silt turbidity of 25 or more milligrams per liter in less than one year following completion and satisfactory development pursuant to § 74:02:04:58, the well driller shall correct the problem.
S.D. Admin. R. 74:02:04:37
General Authority: SDCL 46-2-5, 46-6-20, 46-6-27.
Law Implemented: SDCL 46-6-6.1, 46-6-10, 46-6-20, 46-6-27.