S.D. Admin. R. 70:13:01:12

Current through Register Vol. 51, page 67, December 16, 2024
Section 70:13:01:12 - BIG Default

The commission may determine an LPA to be in default under the BIG conditions or requirements. The department will notify an LPA at least ten calendar days prior to the commissions consideration of default by the LPA, and the LPA will be afforded an opportunity to address the commission. The commission may consider any of the following to be a default under the conditions or requirements of a BIG:

(1) If the LPA knowingly makes any material false statement or report ;
(2) Failure of the LPA to adhere to conditions of the BIG;
(3) Failure of the LPA to provide the department access to documents, reports, or other information required by this chapter;
(4) If funds are not used by the LPA for the project specified in the application; or
(5) Failure of the LPA to comply with the deadlines set under § 70:13:01:10.

S.D. Admin. R. 70:13:01:12

42 SDR 52, effective 10/13/2015; 43 SDR 57, effective 10/17/2016

General Authority: SDCL 32-11-39.

Law Implemented: SDCL 32-11-38, 32-11-39.