Section 70:13:01:04 - Application and approval periods

An LPA shall submit any applications for bridge preservation, rehabilitation, and replacement grants no later than January 2 of each year, and the commission shall consider those applications by April 30 of each year. An LPA shall submit any applications for preliminary engineering grants no later than August 1 of each year, and the commission shall consider those applications by October 30 of each year.