Section 70:12:02:06 - Five-year project list

The county highway and bridge improvement plan or plan update shall include a list of the projects proposed to be undertaken by the county over the next five years . A bridge project shall appear on the project list to be eligible for a bridge improvement grant. Project information shall include:

(1) The location of the project;
(2) The type of project improvement;
(3) Each source of available funding for the project;
(4) The estimate of the cost of the project; and
(5) The year the project is proposed to be built.