S.D. Admin. R. 70:03:01:47

Current through Register Vol. 51, page 67, December 16, 2024
Section 70:03:01:47 - Extended period permit - Over 80,000 pounds on interstate permit

A permit-issuing authority may issue to an applicant an extended period permit which allows the operation on the interstate highway system of a vehicle which exceeds a gross weight of 80,000 pounds. The weight of the vehicle must conform to the tire, axle, and bridge weight requirements in SDCL 32-22-16, 32-22-16.1, and 32-22-21, and the vehicle combination may not exceed the length limits in SDCL 32-22-8.1. Except for a vehicle consisting of a straight truck or tractor-semitrailer combination, the vehicle may not exceed a speed of 65 miles per hour, including all enforcement tolerances.

S.D. Admin. R. 70:03:01:47

2 SDR 37, effective 11/20/1975; 10 SDR 7, effective 7/31/1983; 11 SDR 33, effective 9/3/1984; transferred from

General Authority: SDCL 32-22-42.

Law Implemented: SDCL 32-22-42.