Within 90 days of receiving the completed affidavit for a South Dakota Jobs grant and a determination by GOED that all terms and conditions imposed pursuant to this chapter have been met, GOED shall tender the South Dakota Jobs grant to the project owner or the project owner's assignee. If the project owner or assignee has granted a security interest in the expectation of receipt of a South Dakota Jobs grant, payment shall be made jointly-payable to the project owner or assignee and the holder of the security interest. If GOED requests additional information or documentation from the project owner, the 90 day period shall begin to run from the date of receipt of the additional documents or information.
S.D. Admin. R. 68:02:10:12
General Authority: SDCL 1-16G-5, 1-16G-8(9).
Law Implemented: SDCL 1-16G-5, 1-16G-8(9), 1-16G-48(5).