Costs of work performed by private contractors in emergency/disaster work are eligible costs. Costs incurred under contracts based on cost plus percentage of costs are ineligible costs except where such a delay would extend or create a hazard to health or safety. Justification for this type of contract must be available at the applicant's office of record. State and local taxes on subcontracts are ineligible costs.
S.D. Admin. R. 50:02:01:09
General Authority: SDCL 33-15-24.8.
Law Implemented: SDCL 33-15-24.1.