S.D. Admin. R. 20:10:39:25

Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:39:25 - Pre-test documentation

All pre-test calibration requirements required by §§ 20:10:39:11, 20:10:39:12, and 20:10:39:13 must be completed and documented. A drawing of the dairy is prepared by the qualified testing professional indicating:

(1) The location of the buildings;
(2) Secondary electrical service panels and secondary feeder systems serving cow contact areas;
(3) Transformers and central distribution point;
(4) Existing grounding electrodes, if known;
(5) The location of all cow contact points to be tested;
(6) All remote reference electrodes; and
(7) All primary and secondary neutral test points used in conjunction with the remote reference electrodes.

A list of planned test points is prepared using the applicable form prior to beginning each test. Each test is listed separately and specific reference numbers are given to each planned test point.

S.D. Admin. R. 20:10:39:25

42 SDR 174, effective 6/21/2016

General Authority: SDCL 49-47-2.

Law Implemented: SDCL 49-47-2, 49-47-3.