Section 20:10:37:15 - Pipeline operator's failure to reply

A failure to reply to either an inspection report according to § 20:10:37:09 or an incident report according to § 20:10:37:14 shall be considered consent to the report in its entirety. However. any proposed civil penalty is subject to commission approval.

S.D. Admin. R. 20:10:37:15

36 SDR 57, effective 10/19/2009.

General Authority: SDCL 49-34B-4, 49-34B-19.

Law Implemented: SDCL 49-34B-3, 49-34B-4, 49-34B-5, 49-34B-7, 49-34B-12, 49-34B-19, 49-34B-27.