Section 20:10:36:49 - Tier 3 interconnection completionThe tier 3 application process is complete when:
(1) All tier 3 screening criteria are satisfied and any minor modifications to the EDS that may have been identified are implemented;(2) The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection;(3) There is a successful completion of the witness test, if required;(4) The parties execute a certificate of completion; and(5) An interconnection agreement has been executed.S.D. Admin. R. 20:10:36:49
35 SDR 305, effective 7/1/2009.General Authority: SDCL 49-34A-27, 49-34A-93.
Law Implemented: SDCL 49-34A-27, 49-34A-93.