S.D. Admin. R. 20:10:36:40

Current through Register Vol. 51, page 67, December 16, 2024
Section 20:10:36:40 - Tier 2 application completion

The tier 2 interconnection process is complete when:

(1) All tier 2 screening criteria are satisfied and any minor EDS modifications are implemented;
(2) The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection;
(3) The witness test, if conducted by the public utility, is successful;
(4) The parties execute a certificate of completion; and
(5) An interconnecting agreement has been executed.

S.D. Admin. R. 20:10:36:40

35 SDR 305, effective 7/1/2009.

General Authority: SDCL 49-34A-27, 49-34A-93.

Law Implemented: SDCL 49-34A-27, 49-34A-93.